Grid monitors · Sumatra · G.02

PLN Sumatra interconnected grid and the Batam island system

The Sumatra 275/150 kV system, a north-south backbone from Aceh through Medan, Pekanbaru and Palembang to Lampung, plus the separate Batam-Bintan (Barelang) island grid run by PLN Batam, where Medco Power operates the Panaran gas plants.

Snapshot · coordinates approximate; not an operational topology · as of 26 Jun 2026 · RUPTL 2025–2034; PLN AR 2024; public sources · data 2026-06-26

DC Solutions → Java-Bali grid → Sumatra grid

01 Grid map

Click the map to enable scroll zoom; click a mark for its rating, operator and confidence.

275 kV backbone150 kVBatam island (separate grid)SubstationPlantData center

FIG. 1 Source: RUPTL 2025-2034 / PLN AR 2024 / public sources. Coordinates approximate; not an operational topology. Dataset version 2026-06-26.

02 What the dataset holds

Batam is islanded. The Batam-Bintan-Rempang-Galang (Barelang) 150 kV grid is not synchronously tied to the mainland Sumatra interconnection — it is its own system run by b'right PLN Batam, with Medco Power's Panaran gas plants and PLTU Tanjung Kasam as base-load, and the Nongsa Digital Park subsea-cable DC hub, a Singapore-adjacent AI/edge load.

03 Substation and plant atlas

Sorted by province. Capacity is MW for plants and MVA for substations.

NodeTypekVCapacityRegionNotes