DC Solutions · Calculator · TCO
Total cost of ownership build, colocation or cloud
Five- or ten-year cost of building your own facility, leasing colocation or running in the cloud, from IT load, country, tier, PUE, utilisation, cooling and growth, with each country priced from the engine reference data. Computed in your browser; every figure follows the inputs.
engine RZEngine country reference · basis Turner & Townsend DCCI 2025, CBRE H1 2025, IEA Electricity 2025 · updated 2026-10
DC Solutions → Calculator → TCO
Market rates
Source: Turner & Townsend DCCI 2025, CBRE H1 2025, IEA Electricity 2025
Results
TCO = CAPEX or setup + Σ yearly OPEXN. Virginia · 5 MW, 5 years, Tier III
Headline
By option
Period total
Change any input to compare the options.
Assumptions
Full analysis — Monte Carlo range, cumulative cost by year, sensitivity, strategy and roadmap
Cost by category
period totals, lowest option per row in bold| Cost category | Build | Colocation | Cloud |
|---|---|---|---|
| Adjust inputs above to see detailed cost comparison | |||
02 / Reference
Method
- Build CAPEX
P_IT (MW) · regional cost/MW · tier multiplier (II 0.85, III 1.0, IV 1.35) - Build OPEX
power P_IT · PUE · 8,760 h · $/kWh + staff · salary + maintenance 3 % and insurance 0.7 % of CAPEX + network $20k/MW/mo + 4 % overhead - Colocation
P_IT (kW) · wholesale $/kW/mo · 12 + setup $50k/MW + 1.5 FTE/MW + network $15k/MW/mo + 3 % overhead, escalated yearly - Cloud
P_IT (kW) · $420/kW/mo · 12 · (1 − discount) · (1 + 15 % egress + 10 % support + 2 % other), +2.5 %/yr - Growth
capacity compounds at the growth rate; costs inflate per category each year - Breakeven
first year cumulative build ≤ cumulative colocation
Computed against
Turner & Townsend DCCI 2025CBRE H1 2025Cushman & Wakefield 2025IEA Electricity 2025–2026Glassdoor / PayScale 2025Uptime Institute Tier II–IV
Read further
Technical manual and methodologyGlossaryCAPEX calculatorOPEX calculatorROI calculatorDC market trackerDC SolutionsMy account and saved scenarios
Estimates from 2025–2026 market data (Turner & Townsend, CBRE, Cushman & Wakefield, IEA). Site conditions, vendor terms and market timing move real costs. Not a basis for investment decisions; confirm with a qualified data-center advisor. Runs in your browser. Independent research; not affiliated with any current or former employer. Privacy · Terms.