DC Solutions · Workbench · RFS readiness
Ready-for-service readiness gate by gate, from your own evidence
Track a commissioning program through gates G0 to G7: weighted requirements and evidence per delivery unit, defects by severity, test packages, procedures and a forecast RFS date. The gate engine runs in your browser and the project is stored there.
engine RFS gate engine (in page) · basis Cx levels L0–L6, NETA ATS, NFPA 72 · confidence and forecast are directional
DC Solutions → Workbench → Setup
Program status
gate engine · this browserFull analysis — test packages (L0–L6) and customer overlay rules
| Unit ? | Type ? | Target Gate | Target Date | Blockers ? | Confidence ? |
|---|
| ID | Title | Unit | Severity ? | Status ? | Owner | Age ? | Gate Impact ? |
|---|
02 / Reference
Method
- Readiness
Σ weight of requirements with accepted evidence ÷ Σ weight, per unit and gate - Confidence
100 − 18·critical − 8·major − 7·missing mandatory evidence − 6·missing sign-offs − 5·retests − 3·overdue defects − 2·unconfirmed overlays, held to 5–100 % - Blocked
open critical defect, prior gate not approved, or an unresolved hard overlay (source A/B) - At risk
open major defect, missing mandatory evidence or an unconfirmed overlay - Days to next gate
base days · archetype factor + 3·critical + 1·major + 1·missing evidence + 2·missing sign-offs + 2·retests + 1·witness tests + ⌈0.5·overlays⌉ - Project RFS
the latest unit forecast date
Computed against
Commissioning levels L0–L6NETA ATS acceptance testingNFPA 72 fire alarm testingUptime Institute Tier I–IV
Read further
Technical manual and methodologyCx calculatorSpares readinessGlossaryDC SolutionsMy account
Directional forecasts for engineering workflow. They do not replace customer standards, regulatory review, certification or formal project controls, and the dates are not contractual. The project is stored in this browser; nothing is sent to a server. Independent research; not affiliated with any current or former employer. Privacy · Terms.