← All incidents
Incident dossier · Rank #6 · magnitude 8.6

OVHcloud SBG2 Strasbourg Data-Center Fire (10 March 2021)

OVHcloud 2021-03-10 restoration time not established FirePower

Summary

In the early hours of 10 March 2021 a fire broke out in a ground-floor energy room at OVHcloud's SBG2 facility in Strasbourg, where the site's UPS units and their lead-acid battery banks were housed. Video surveillance and the fire panel traced the initiating event to a near-simultaneous electrical fault on UPS2 and its connected batteries. With no automatic suppression system in any of the five campus buildings, and a free-cooling design that used intumescent-treated raw-wood floors and single-skin cladding to aid airflow, the fire spread through the entire structure. De-energisation was slow because there was no accessible general site cut-off, forcing the grid operator to isolate an upstream substation; current was still present in the burning building well after the cut order. SBG2 was destroyed in its entirety, four of twelve rooms in adjacent SBG1 were partially destroyed, and the SBG2–SBG3 inter-building link was impacted. Roughly 30,000 servers were lost and about 3.6 million websites went offline. There were no casualties or injuries. French investigator BEA-RI could establish the fault location but not its precise cause, leaving several hypotheses open pending a court-expert examination.

Users affected
~3.6 million websites taken offline; ~30,000 servers destroyed
Duration
Faults and first alarm 00h35 9 Mar; SBG2 total loss, no customer service restoration time given.
Financial
Undetermined — total damages were still being assessed by a Strasbourg court-appointed expert panel at report time; no authoritative total was published
Scope
Catastrophic (total facility loss)
Site
SBG2 (Strasbourg campus) · Strasbourg, France
Services down
Bare Metal dedicated servers, Public Cloud instances, VPS, Hosted Private Cloud, customer-hosted websites and databases

How the defences failed

How the defences failed — OVHcloud8 failure modes in the order the sequence of events first shows them, 0 latent conditions with no moment in the record, ending in the outcome: SBG2 lost · 3.6M websites offline.ACTIVE — IN THE ORDER THE RECORD SHOWS THEMFM-01 · RPN 350Inverter and battery faultS10 · O5 · D7FM-02 · RPN 300No automatic suppressionS10 · O5 · D6FM-08 · RPN 40Staff exposed to fireS10 · O2 · D2FM-04 · RPN 432Site stays live over an hourS9 · O6 · D8FM-05 · RPN 384Fire water far too lowS8 · O6 · D8FM-03 · RPN 270Envelope spreads the fireS9 · O5 · D6FM-06 · RPN 432Backups in the same buildingS8 · O6 · D9FM-07 · RPN 192Second fire in SBG1S6 · O4 · D8OUTCOMESBG2 lost · 3.6M websites offlineLEGENDHigh priorityMedium or low priority, no published actionMedium or low priorityNext failure in the record
How the defences failed — OVHcloud8 failure modes in the order the sequence of events first shows them, 0 latent conditions with no moment in the record, ending in the outcome: SBG2 lost · 3.6M websites offline.ACTIVE — RECORD ORDERFM-01 · RPN 350Inverter and battery faultS10 · O5 · D7FM-02 · RPN 300No automatic suppressionS10 · O5 · D6FM-08 · RPN 40Staff exposed to fireS10 · O2 · D2FM-04 · RPN 432Site stays live over an hourS9 · O6 · D8FM-05 · RPN 384Fire water far too lowS8 · O6 · D8FM-03 · RPN 270Envelope spreads the fireS9 · O5 · D6FM-06 · RPN 432Backups in the same buildingS8 · O6 · D9FM-07 · RPN 192Second fire in SBG1S6 · O4 · D8OUTCOMESBG2 lost · 3.6M websites offlineLEGENDHigh priorityMedium or low priority, no published actionMedium or low priorityNext failure in the record
Every failure mode of the FMEA below. Active modes run in the order the sequence of events first shows them — record order, not a proof of cause; latent modes were in place before the event. Red outline: high priority. Dashed: no published corrective action.
Magnitude sub-scores (0–10)Magnitude sub-scores (0–10)Users 9Users affected (0–10) — breadth of the user/customer population impacted. — scored 9/10.Financial 8Financial impact (0–10) — direct + consequential cost. — scored 8/10.Duration 8Outage duration (0–10), from the measured duration by fixed bands: <1 h 3 · 1–4 h 4 · 4–12 h 5 · 12–24 h 6 · 1–3 d 7 · 3–7 d 8 · 7–30 d 9 · >30 d 10; no customer downtime 1. — scored 8/10.Blast 9Blast radius (0–10) — how wide the fault propagated across systems/regions. — scored 9/10.
Magnitude 8.6 = blast 9×0.35 + users 9×0.25 + financial 8×0.20 + duration 8×0.20 (sub-scores 0–10 · weighted composite)

Extreme user and blast-radius impact — an entire data center destroyed with ~3.6M websites offline and ~30k servers lost, plus collateral damage to SBG1 and the SBG3 link. Financial score reflects a very large but formally unquantified loss (court-expert assessment still open). Duration score spans the ~9.5h fire fight and the multi-week service-restoration tail (recovery from 17 Mar; ~99% of key products re-delivered by 23 Apr).

All 12 impact metrics
SBG2 lead-acid battery bank~800 batteries, ~30 kg each
Detection-to-safe-de-energisation gapfirst alarm 00h35 -> site electrically secured ~02h30 (~1h55); full site dead only at 03h28
On-site fire-water supplysingle public hydrant, <60 m3/h; no owned reserve, no canal pumping
Fireboat EUROPA capacity3 pumps at 15,000 L/min + 2 foam/water lances at 4,500 L/min each
Foam concentrate consumed~4000 L
Personnel / casualtiesnight crew evacuated safely; 0 fatalities, 0 injuries
Building lossSBG2 (6-level) total loss; SBG1 partially damaged (4 of 12 rooms per BEA-RI); SBG3/SBG4 intact
Customer impact~3.6 million websites and 464,000 domain names ceased responding on 10 Mar
SBG2 capacitybuilt 2016, capacity ~30,000 physical servers
Estimated damage~EUR105 million
Litigation (first-instance, later cut on appeal)~EUR250k combined to two customers in 2023 (EUR100k Bati Courtage; ~EUR145k Bluepad), reduced to a few hundred euros each on appeal under contractual caps; 130+ in class action
Fire durationalarm 00h35 -> controlled ~06h45/07h00 -> extinguished ~10h02 (~9.5h)

Sequence of events

  1. TRIGGER Ambient sensors on the rear of the SBG2 inverters log an anomalous humidity spike - later cited as supporting the liquid/humidity short-circuit hypothesis for ASI2.
  2. TRIGGER A further marked humidity rise is recorded just after 00h30, followed by continuous temperature increase on the inverters ahead of failure.
  3. DETECTION Near-simultaneous electrical faults strike the lead-acid batteries AND inverter ASI2 in two separate ground-floor energy rooms; first fire alarm reaches the site security PC. Optical and aspirating detectors 'ont parfaitement joue leur role'.
  4. DETECTION Security guard reaches ground-floor energy room no.2 and finds thick black smoke; aspirating detectors sense smoke on all floors within ~15 minutes.First responder
  5. MITIGATION SBG2 evacuated; the small night crew is accounted for - zero victims, zero injuries.Safety officer
  6. DETECTION OVH guard places the emergency call to the fire service (SIS/SDIS 67).First responder
  7. MITIGATION Order given to cut electrical supply to the whole site - but no accessible general cut-off exists to execute it quickly.
  8. MITIGATION Firefighters arrive, observe 'des arcs electriques dans le local energie', deploy a single water lance while awaiting de-energisation, and judge the building design will not permit containment.Fire & rescue commander
  9. MITIGATION SBG2 electrical supply cut by OVH.Authorised electrical person
  10. CASCADE Water applied at the SBG2 facade; backup energies of SBG3/SBG1/SBG4 cut by OVH; SBG2 first floor is fully involved less than an hour after the first alarm.Authorised electrical person
  11. CASCADE Whole first floor taken; upper-floor spread now unstoppable; two lances working (ground level plus an aerial ladder).
  12. MITIGATION Fireboat EUROPA requested because on-site water means are insufficient (single hydrant <60 m3/h).Fire & rescue commander
  13. MITIGATION SER cuts remotely at the upstream source substation (client HT posts inside the fire zone could not be operated) - remote cut becomes effective.Utility / grid operator
  14. IMPACT Generalized flashover of SBG2; upper-floor temperature sensors saturate.
  15. IMPACT Current is STILL present in the fully-ablaze building 2 - residual lead-acid battery supply (~20 min) and auto-started diesel generators keep it live.
  16. MITIGATION Site judged electrically secured; massive water attack finally engaged - but SBG2 is fully involved and already spreading to SBG1 and SBG3.Fire & rescue commander
  17. MITIGATION Fireboat EUROPA arrives, adding 3 pumps at 15,000 L/min and 2 foam/water lances at 4,500 L/min each - described as decisive in sparing SBG1/SBG3.Fire & rescue commander
  18. CASCADE Fire spreads to SBG1 (container-type build, losing 4 of 12 rooms) and SBG3 (protected by a 2-hour firewall, though fire-stop doors were held open, degrading it).
  19. IMPACT 'A partir de 03h28, il n'y a plus de courant sur le site' - the site is finally fully dead.
  20. RECOVERY Fire declared 'maitrise' (under control).Fire & rescue commander
  21. RECOVERY Fire extinguished; ~4000 L of foam concentrate consumed over the intervention.Fire & rescue commander
  22. RESTORED SBG2 declared a total loss; all customer data and backups stored in SBG2 lost. Netcraft measured ~3.6 million websites / 464,000 domains ceasing to respond that morning.
  23. CASCADE A second fire breaks out in a battery room of SBG1 ('un nouvel incendie a lieu dans un local a batteries du batiment SBG1'), forcing a fresh site power-down and delaying recovery.
  24. RESTORED First-instance courts awarded ~EUR100k (Bati Courtage, Lille 26 Jan 2023) and ~EUR145k (Bluepad, 9 Mar 2023) - together ~EUR250k to two customers; both were drastically cut on appeal (2025-2026) under OVH's contractual liability caps (six months' fees). 130+ customers pursue a class action.Customer

Response by role

11 roles/13 recorded actions/41 playbook actions across 8 failure modes/no recorded action: Incident commander, Service recovery lead, Communications lead, Crisis lead, Authority / investigator

What each role did

Roles the sequence of events shows acting; every entry quotes its source line. Select a time to jump to it.

Role
Detect
Contain
Recover
First responderOVH night security guard at SBG
  • Reaches energy room 2 two minutes after the alarm and finds thick black smoke
  • Calls the fire service, seven minutes after the first alarm
no record
no record
Fire & rescue commanderSIS / SDIS 67, Bas-Rhin fire and rescue
no record
  • Arrives at 00h59, sees arcing in the energy room, holds to one lance until the site is de-energised
  • Calls the fireboat EUROPA: the single hydrant gives under 60 m3/h
  • Starts the massive water attack once the site is judged electrically secured
  • Fireboat adds 3 pumps and 2 foam/water lances, decisive in sparing SBG1 and SBG3
  • Declares the fire under control
  • Extinguishes the fire; about 4,000 L of foam concentrate used
Authorised electrical personOVH staff who isolated SBG2 and the backup supplies
no record
  • Cuts SBG2's supply, 38 minutes after the alarm
  • Cuts the backup supplies of SBG1, SBG3 and SBG4
no record
Utility / grid operatorSER, the Strasbourg grid operator
no record
  • Cuts the site at the upstream substation; the HT posts inside the fire zone cannot be operated
no record
Safety officerWhoever evacuated SBG2 and counted the night crew — not named
no record
  • Evacuates SBG2 and accounts for the night crew: no victims, no injuries
no record
CustomerOVHcloud customers hosted in SBG
no record
no record
  • Over 130 customers pursue a class action after first-instance awards were cut on appeal

Role by role

Recorded actions / playbook actions per role. A role with 0 recorded actions does not appear in the sources.

OVH night security guard at SBG — Meets the first alarm: on-shift technician or security in a facility, on-call engineer in a service.

On the record

  1. Reaches energy room 2 two minutes after the alarm and finds thick black smokeSecurity guard reaches ground-floor energy room no.2 and finds thick black smoke
  2. Calls the fire service, seven minutes after the first alarmOVH guard places the emergency call to the fire service

Playbook analyst guidance by failure mode, not a record of what happened

Detect
  • FM-01Treat an inverter humidity or temperature alarm as a call-out: go, look, log and escalateUptime OS
  • FM-02Where there is no suppression, call the fire service on the first confirmed alarm, before inspectingNFPA 75
  • FM-03Report smoke on upper floors as fire spread, not as a separate alarmNFPA 72
  • FM-07Keep a fire watch on battery rooms for the whole recoveryNFPA 855
  • FM-08Investigate an alarm in pairs and withdraw on visible smokeNFPA 1561

OVH site command on the night — no one is named in the record — Owns every decision until formally relieved: site duty manager on scene, or the declared IC of a service incident.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Detect
  • FM-04Know which sources feed each building — grid, UPS, batteries, generators — before the fire service asksNFPA 70E
Contain
  • FM-05Give the fire service the site water plan: hydrants, flows, canal accessNIMS / ICS
  • FM-01Declare the incident, take command and order isolation of the energy room before the fire service arrivesNIMS / ICS
  • FM-02Meet the fire service with one briefing: seat of fire, what is still live, water, peopleNIMS / ICS
Recover
  • FM-07Re-plan the restoration after the second power-downNIMS / ICS

SIS / SDIS 67, Bas-Rhin fire and rescue — External incident commander for fire, rescue and hazardous materials; works in unified command with the site.

On the record

  1. Arrives at 00h59, sees arcing in the energy room, holds to one lance until the site is de-energiseddeploy a single water lance while awaiting de-energisation
  2. Calls the fireboat EUROPA: the single hydrant gives under 60 m3/hFireboat EUROPA requested
  3. Starts the massive water attack once the site is judged electrically securedmassive water attack finally engaged
  4. Fireboat adds 3 pumps and 2 foam/water lances, decisive in sparing SBG1 and SBG3Fireboat EUROPA arrives
  5. Declares the fire under controlFire declared
  6. Extinguishes the fire; about 4,000 L of foam concentrate usedFire extinguished

Playbook analyst guidance by failure mode, not a record of what happened

Detect
  • FM-05Measure hydrant flow on arrival and call for more water at once if it is shortNFPA 1561
Contain
  • FM-04Get isolation confirmed by the site's authorised person before committing massive waterNFPA 1561
  • FM-05Bring in a fireboat or tanker relay as soon as on-site flow is known to be shortNFPA 1561
  • FM-02Hold water off live equipment until the site confirms isolationNFPA 1561
  • FM-03Switch to defending the neighbouring buildings once the origin building cannot be heldNFPA 1561
  • FM-07Treat the recovering site as a live fire risk until the batteries are clearedNFPA 1561
  • FM-08Take the head count from the site before sending crews insideNFPA 1561

OVH staff who isolated SBG2 and the backup supplies — Switching, isolation and lock-out of power sources, and safe re-energisation.

On the record

  1. Cuts SBG2's supply, 38 minutes after the alarmSBG2 electrical supply cut by OVH.
  2. Cuts the backup supplies of SBG1, SBG3 and SBG4backup energies of SBG3/SBG1/SBG4 cut by OVH

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-04Install an accessible general cut-off and drill the isolation sequenceImprovement #2
  • FM-01Find the cause of recurring by-pass trips before an inverter goes back into serviceCorrection of errors #3
  • FM-07Inspect and isolate surviving battery rooms before anything is re-energisedNFPA 855
Detect
  • FM-01Supervise every battery string and alarm on drift in voltage, temperature or impedanceNFPA 855Improvement #5
Contain
  • FM-04Isolate in a fixed order: grid, generators with auto-start blocked, UPS output, battery DCEN 50110-1Contributing factor #6
  • FM-01Open the UPS input, output and battery DC breakers of the faulted stringNFPA 70E
Recover
  • FM-04Re-energise only after inspection and release by the fire serviceNFPA 70E

SER, the Strasbourg grid operator — External owner of the supply: switching at the substation, load shedding, restoration.

On the record

  1. Cuts the site at the upstream substation; the HT posts inside the fire zone cannot be operatedSER cuts remotely at the upstream source substation

Playbook analyst guidance by failure mode, not a record of what happened

Contain
  • FM-04Cut at the substation on request when the site's own HT posts are inside the fire zoneNIMS / ICS

Whoever evacuated SBG2 and counted the night crew — not named — Head count, exclusion zones, PPE and the go / no-go for re-entry.

On the record

  1. Evacuates SBG2 and accounts for the night crew: no victims, no injuriesSBG2 evacuated; the small night crew is accounted for

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-02Fit automatic suppression to energy rooms and data hallsNFPA 75Correction of errors #1
  • FM-03Treat batteries and their chargers as one fire unit and compartment itImprovement #4
  • FM-08Drill night evacuation with the real night staffingUptime OS
Contain
  • FM-03Close fire-stop doors behind the evacuation; never leave them wedged openContributing factor #7
  • FM-08Account for everyone at the assembly point and report the count to the fire serviceNIMS / ICS
Recover
  • FM-02Keep staff out until the fire service hands the building backNFPA 1561
  • FM-08Keep staff out of live or smoke-damaged buildings until releasedNFPA 70E

OVHcloud support and recovery teams — Restores customer service: failover, workload moves, capacity, backlog drain.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Detect
  • FM-06List every customer whose only backup was in SBG2 as soon as the building is lostISO 22301
Recover
  • FM-06Provision replacement servers in other sitesISO 22301

OVHcloud public updates — not in this sequence of events — Status page, customer notices, regulators and press; one voice, timed updates.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Contain
  • FM-06Tell those customers directly what is lost, what is not, and when the next update comesISO 22301

OVHcloud executive leadership — Executive owner of business continuity: invokes plans, commits money, speaks to authorities.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-05Provide owned fire-water reserves or canal pumping sized for a building fireCorrection of errors #4
Recover
  • FM-05Bring water resources up to the regulated requirement before rebuildingImprovement #3
  • FM-03Audit every site for fire vulnerability and carry the findings into rebuild standardsImprovement #6

OVHcloud customers hosted in SBG — The tenant or service user: their own redundancy, backups and continuity plan.

On the record

  1. Over 130 customers pursue a class action after first-instance awards were cut on appeal130+ customers pursue a class action

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-06Keep at least one backup copy in another building or regionNIST SP 800-34Correction of errors #6
Recover
  • FM-06Restore from off-site copies into another regionNIST SP 800-34

BEA-RI, the French industrial-accident investigator — Regulator, investigator or court that establishes cause and obligations after the event.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Recover
  • FM-01Establish the ignition mechanism and publish itCorrection of errors #5

Failure mode & effects analysis (FMEA)

The SBG campus fire chain at OVHcloud Strasbourg: the UPS (ASI2) and lead-acid battery energy rooms where the fire started, their monitoring and maintenance, fire detection and the absent automatic suppression, the free-cooling building envelope and compartmentation, electrical isolation of the site, fire-water supply, the second battery-room fire in SBG1, and customer data placement. Analysed retrospectively from the BEA-RI technical investigation (accessed via secondary relays this pass; its granular times and figures are not corroborated by a second source) and the press record in this dossier. BEA-RI established where the fire started but not why: the ignition mechanism is undetermined and was deferred to judicial expertise. Only one corrective action (automatic suppression across the SBG estate) is recorded as an OVHcloud commitment, and its completion is not independently verified; the other actions are BEA-RI recommendations with unverified status, so those modes are shown as residual risk.

8 failure modes/6 high priority/1 of 8 with a published action/total RPN 2400 → 2180 (−9%)

RPN = S × O × D, worst first. Thin bar: after the published action.
FM-04no published action432
FM-06no published action432
FM-05no published action384
FM-01no published action350
FM-02300 → 80
FM-03no published action270
FM-07no published action192
FM-08no published action40
Severity × occurrence. Lines bound the medium and high zones.
1122334455667788991010Occurrence →Severity →FM-08 Staff exposed to smoke, fire or live electrical equipment (S10 O2 D2)08FM-01 Near-simultaneous electrical faults on inverter ASI2 and on the lead-acid batteries, in two separate rooms, ignite a fire (S10 O5 D7); FM-02 No automatic suppression exists, so a detected fire cannot be fought until the building is de-energised and the fire service commits water (S10 O5 D6)01, 02FM-03 The free-cooling envelope lets fire and smoke climb vertically at high speed, and passive barriers are degraded (S9 O5 D6)03FM-04 The building stays live for well over an hour after the cut order (S9 O6 D8)04FM-05 Water supply is far below what a building-scale fire needs (S8 O6 D8); FM-06 Primary data and its only backups sit in the same building (S8 O6 D9)05, 06FM-07 A second fire breaks out in a battery room of SBG1 (S6 O4 D8)07
Caught only after impactD ≥ 8
4 of 8
Actions that cut occurrenceO lowered
1
Actions that cut detectionD lowered
1
Actions that cut severityblast radius unchanged
0
FM-04 The building stays live for well over an hour after the cut orderSite electrical isolation (general cut-off, HT posts, generator logic, battery residual supply) 9·6·8 432 —
Function
De-energise the burning building within minutes so firefighters can apply water safely
Effect
Cut ordered ~00h58; the upstream substation cut is effective ~01h50; current is still present at 02h14; massive water attack starts only ~02h30, after flashover at ~02h00; the site is fully dead only at 03h28
Cause
No accessible general site cut-off; client HT posts inside the fire zone could not be operated; diesel generators slaved to supply continuity auto-started and had to be neutralised by hand; charged lead-acid batteries supplied about 20 minutes of residual power
Prevention in place
None recorded for fast whole-site isolation
Detection in place
Firefighters observed electrical arcing in the energy room on arrival at 00h59; the delay was found during the incident
S 9
The dossier calls de-energisation the true bottleneck: it set the moment water could be committed, which came after flashover. Scored 9, not 10, because the facility loss is already carried at 10 upstream.
O 6
The missing cut-off and the generator logic are standing conditions that any emergency isolation exercises, weakly guarded: 'occasional'.
D 8
Nothing recorded tested emergency isolation beforehand; the obstacles surfaced as responders tried to make the site safe: 'detected after impact'.

Corrective action

  • Provide an accessible general electrical cut-off and separate UPS from associated batteries into fire-rated rooms (BEA-RI recommendation; implementation unverified) Correction of errors #2
  • Install an easily accessible general site cut-off and drill electrical-securing procedures Improvement #2

Who acts — playbook

Prevent
  • Authorised electrical person Install an accessible general cut-off and drill the isolation sequenceImprovement #2
Detect
  • Incident commander Know which sources feed each building — grid, UPS, batteries, generators — before the fire service asksNFPA 70E
Contain
  • Authorised electrical person Isolate in a fixed order: grid, generators with auto-start blocked, UPS output, battery DCEN 50110-1Contributing factor #6
  • Utility / grid operator Cut at the substation on request when the site's own HT posts are inside the fire zoneNIMS / ICS
  • Fire & rescue commander Get isolation confirmed by the site's authorised person before committing massive waterNFPA 1561
Recover
  • Authorised electrical person Re-energise only after inspection and release by the fire serviceNFPA 70E

On the record at this failure

  • Utility / grid operator Cuts the site at the upstream substation; the HT posts inside the fire zone cannot be operated

Evidence

  • Contributing factor #2Absence of a readily accessible general site electrical cut-off: isolation required tripping the upstream source substation because client-owned HT posts sat inside the fire zone and could not be operated, delaying safe de-energisation from the ~00h58 cut order to ~02h30. [BEA-RI report]
  • Contributing factor #6Diesel generators slaved to supply continuity auto-started despite the fire and had to be manually neutralized to keep them from restarting on the cut, prolonging the live-electrical condition. [BEA-RI report]
  • Sequence of events #7~00h58 — Order given to cut electrical supply to the whole site - but no accessible general cut-off exists to execute it quickly.
  • Sequence of events #13~01h50 — SER cuts remotely at the upstream source substation (client HT posts inside the fire zone could not be operated) - remote cut becomes effective.
  • Sequence of events #1502h14 — Current is STILL present in the fully-ablaze building 2 - residual lead-acid battery supply (~20 min) and auto-started diesel generators keep it live.
  • Metric #2Detection-to-safe-de-energisation gap: first alarm 00h35 -> site electrically secured ~02h30 (~1h55); full site dead only at 03h28
  • Technical deep-dive“at 02h14 there was STILL current in the fully-ablaze building 2”
FM-06 Primary data and its only backups sit in the same buildingCustomer data placement and backups 8·6·9 432 —
Function
Keep a recoverable copy of customer data outside the failed facility
Effect
All customer data and backups stored in SBG2 are lost; about 3.6 million websites and 464,000 domains stop responding; customers who relied solely on SBG2 lose data outright, and court awards were later cut on appeal under contractual liability caps
Cause
Many customers had no off-site or geo-redundant backup
Prevention in place
None recorded as a default
Detection in place
Customer impact
S 8
Permanent data loss for the affected customers is a full outage with no recovery for them; scored 8 so the facility loss carried in FM-01 to FM-04 is not counted again at 10.
O 6
Single-site backup is a common, weakly guarded customer choice: 'occasional'. The dossier records OVHcloud expanding backup offerings per its public messaging, not verified and with uptake unknown, so no reduction is claimed.
D 9
The gap was found only when the building burned: 'detected only through customer impact'.

Corrective action

  • Advise and enable customers on geo-redundant backups (default off-site backup offering); expansion stated in public messaging, not verified Correction of errors #6

Who acts — playbook

Prevent
  • Customer Keep at least one backup copy in another building or regionNIST SP 800-34Correction of errors #6
Detect
  • Service recovery lead List every customer whose only backup was in SBG2 as soon as the building is lostISO 22301
Contain
  • Communications lead Tell those customers directly what is lost, what is not, and when the next update comesISO 22301
Recover
  • Service recovery lead Provision replacement servers in other sitesISO 22301
  • Customer Restore from off-site copies into another regionNIST SP 800-34

On the record at this failure

  • Customer Over 130 customers pursue a class action after first-instance awards were cut on appeal

Evidence

  • Contributing factor #9Customer-side resilience gap: many customers had no off-site/geo-redundant backup, so the SBG2 total loss destroyed both primary data and the only copies for those customers. [Wikipedia en]
  • Sequence of events #2210 Mar, morning — SBG2 declared a total loss; all customer data and backups stored in SBG2 lost. Netcraft measured ~3.6 million websites / 464,000 domains ceasing to respond that morning.
  • Metric #8Customer impact: ~3.6 million websites and 464,000 domain names ceased responding on 10 Mar
  • Sequence of events #242023-2026 — First-instance courts awarded ~EUR100k (Bati Courtage, Lille 26 Jan 2023) and ~EUR145k (Bluepad, 9 Mar 2023) - together ~EUR250k to two customers; both were drastically cut on appeal (2025-2026) under OVH's contractual liability caps (six months' fees). 130+ customers pursue a class action.
FM-05 Water supply is far below what a building-scale fire needsOn-site fire-water supply 8·6·8 384 —
Function
Deliver enough water for a widespread-fire scenario once the site is safe
Effect
Fire service works with one or two lances; the fireboat EUROPA is requested ~01h49 and arrives ~02h57, after which it is described as decisive in sparing SBG1 and SBG3
Cause
A single public hydrant delivering under 60 m3/h, no owned water reserve and no pumping means from the Rhine canal
Prevention in place
None recorded beyond the public network
Detection in place
Found during the incident when on-site means proved insufficient
S 8
It limited the attack on a fire that was already destroying SBG2 and spreading; its own contribution is the extent of damage to neighbouring buildings, so it is scored below the modes that carry the facility loss.
O 6
A standing under-provision exercised by any large fire, weakly guarded: 'occasional'.
D 8
The shortfall was recognised only once firefighters needed the water: 'detected after impact'.

Corrective action

  • Provision owned fire-water reserves or canal pumping sized to the site (BEA-RI recommendation; status unverified) Correction of errors #4
  • Provide on-site extinguishing-water reserves or canal-pumping capability for a widespread-fire scenario Improvement #3

Who acts — playbook

Prevent
  • Crisis lead Provide owned fire-water reserves or canal pumping sized for a building fireCorrection of errors #4
Detect
  • Fire & rescue commander Measure hydrant flow on arrival and call for more water at once if it is shortNFPA 1561
Contain
  • Incident commander Give the fire service the site water plan: hydrants, flows, canal accessNIMS / ICS
  • Fire & rescue commander Bring in a fireboat or tanker relay as soon as on-site flow is known to be shortNFPA 1561
Recover
  • Crisis lead Bring water resources up to the regulated requirement before rebuildingImprovement #3

On the record at this failure

  • Fire & rescue commander Calls the fireboat EUROPA: the single hydrant gives under 60 m3/h
  • Fire & rescue commander Fireboat adds 3 pumps and 2 foam/water lances, decisive in sparing SBG1 and SBG3

Evidence

  • Contributing factor #5Grossly insufficient fire-water: a single public hydrant delivering under 60 m3/h, with no owned water reserve and no pumping means from the Rhine canal, forcing reliance on the fireboat EUROPA. [BEA-RI report]
  • Metric #3On-site fire-water supply: single public hydrant, <60 m3/h; no owned reserve, no canal pumping
  • Sequence of events #12~01h49 — Fireboat EUROPA requested because on-site water means are insufficient (single hydrant <60 m3/h).
  • Sequence of events #17~02h57 — Fireboat EUROPA arrives, adding 3 pumps at 15,000 L/min and 2 foam/water lances at 4,500 L/min each - described as decisive in sparing SBG1/SBG3.
FM-01 Near-simultaneous electrical faults on inverter ASI2 and on the lead-acid batteries, in two separate rooms, ignite a fireUPS ASI2 and lead-acid battery bank (ground-floor energy rooms) 10·5·7 350 —
Function
Carry the IT load through supply disturbances without itself becoming a source of fault
Effect
Fire starts in the energy rooms at 00h35 and, through the defences that failed below, ends in the total loss of SBG2, partial loss of SBG1 and about 3.6 million websites offline
Cause
Undetermined. BEA-RI lists candidate mechanisms for ASI2 (liquid or humidity from the nearby cooling system, the same-morning maintenance intervention, operation outside normal ranges) without concluding; the battery fault cause is also not established
Prevention in place
Maintenance of ASI2 in the days before and on the morning of the fire, prompted by recurring unexplained by-pass trips; return-to-service reports noted nothing singular
Detection in place
Ambient humidity and temperature sensors behind the inverters logged anomalies from about 23h15, but no action on them is recorded; the batteries had no supervision; the fault itself was detected as a fire alarm at 00h35
S 10
This is the initiating event of the loss of an entire facility plus damage to a neighbouring building: the rubric's 10. No one was hurt, but the facility-loss criterion alone reaches 10.
O 5
Between 'infrequent' and 'occasional': ASI2 had recurring unexplained by-pass trips, a weakly guarded condition, but BEA-RI notes internal short-circuits are rare on lead-acid chemistry and the mechanism is undetermined, so it is held at 5.
D 7
Between 'detected at onset' (6) and 'after impact' (8): precursor humidity and temperature readings existed, but with no battery supervision and no retained inverter operating parameters nothing turned them into a warning before the fire alarm.

Corrective action

  • Add UPS and battery supervision and operating-parameter logging; find the cause of recurring by-pass trips before returning an inverter to service (BEA-RI lesson; status unverified) Correction of errors #3
  • Deploy battery monitoring with manufacturer-based preventive-maintenance and replacement rules Improvement #5

Who acts — playbook

Prevent
  • Authorised electrical person Find the cause of recurring by-pass trips before an inverter goes back into serviceCorrection of errors #3
Detect
  • First responder Treat an inverter humidity or temperature alarm as a call-out: go, look, log and escalateUptime OS
  • Authorised electrical person Supervise every battery string and alarm on drift in voltage, temperature or impedanceNFPA 855Improvement #5
Contain
  • Incident commander Declare the incident, take command and order isolation of the energy room before the fire service arrivesNIMS / ICS
  • Authorised electrical person Open the UPS input, output and battery DC breakers of the faulted stringNFPA 70E
Recover
  • Authority / investigator Establish the ignition mechanism and publish itCorrection of errors #5

Evidence

  • Root cause“The PRECISE failure mechanism was NOT established by BEA-RI”
  • Sequence of events #1~23h15 (09 Mar) — Ambient sensors on the rear of the SBG2 inverters log an anomalous humidity spike - later cited as supporting the liquid/humidity short-circuit hypothesis for ASI2.
  • Sequence of events #300h35 — Near-simultaneous electrical faults strike the lead-acid batteries AND inverter ASI2 in two separate ground-floor energy rooms; first fire alarm reaches the site security PC. Optical and aspirating detectors 'ont parfaitement joue leur role'.
  • Contributing factor #3MAINTENANCE / MONITORING GAP: the faulted inverter ASI2 had recurring, unexplained by-pass-mode trips and was serviced the very morning of the fire; the lead-acid batteries had NO scrutation/supervision, and OVH could not produce the inverters' operating parameters at the moment of failure. [BEA-RI report]
  • Contributing factor #8UPS and its associated batteries were located in DIFFERENT rooms, and two near-simultaneous departures occurred across both spaces, complicating any single-point containment. [BEA-RI report]
  • Reference #2 · official-postmortem“L'incendie a pris naissance au sein des locaux qui abritent les batteries et les ASI”
FM-02 No automatic suppression exists, so a detected fire cannot be fought until the building is de-energised and the fire service commits waterFire protection in energy rooms and data halls 10·5·6 300 80
Function
Attack a fire at its source before it leaves the room of origin
Effect
Detection works and the building is evacuated by 00h39, but nothing acts on the fire; the first floor is fully involved within an hour and SBG2 reaches generalised flashover around 02h00
Cause
A deliberate design choice to fit no automatic fire-suppression system (sprinkler, water mist or gas) in any of the five SBG buildings
Prevention in place
Optical point and aspirating smoke detection, manual call points, hand extinguishers
Detection in place
Optical and aspirating detectors alarmed at 00h35 and traced smoke to all floors within about 15 minutes
S 10
The dossier's own analysis names the suppression void as the decisive finding between an energy-room fire and the loss of the facility: the rubric's 10.
O 5
The absence is a standing design condition, but it only produces this failure when an ignition occurs, which is infrequent; scored 5, between 'infrequent' and 'occasional'.
D 6
Detection performed at onset, as BEA-RI credits, but detection without suppression only enabled evacuation: 'detected at onset, not prevented'.

Corrective action

  • Fit automatic fire suppression to all energy and battery rooms and data halls across the SBG estate and rebuild Correction of errors #1
  • Rebuild energy rooms and buildings with automatic fire suppression and proper fire-behaviour construction Improvement #1

After action: S10 · O2 · D4 → RPN 80. Automatic suppression in the energy rooms would act on a fire without waiting for de-energisation, so an unsuppressed fire becomes guarded by design (O 5→2) and the response starts before spread (D 6→4). Severity is unchanged: if suppression failed, the outcome would be the same. OVHcloud's commitment is recorded from public statements with independent completion not verified, so the reduction is a claim about the action, not a confirmed outcome.

Who acts — playbook

Prevent
  • Safety officer Fit automatic suppression to energy rooms and data hallsNFPA 75Correction of errors #1
Detect
  • First responder Where there is no suppression, call the fire service on the first confirmed alarm, before inspectingNFPA 75
Contain
  • Incident commander Meet the fire service with one briefing: seat of fire, what is still live, water, peopleNIMS / ICS
  • Fire & rescue commander Hold water off live equipment until the site confirms isolationNFPA 1561
Recover
  • Safety officer Keep staff out until the fire service hands the building backNFPA 1561

Evidence

  • Contributing factor #1No automatic fire-suppression system in ANY of the five SBG buildings (no sprinkler, water mist, or gas inerting) - a deliberate design choice per BEA-RI; the energy rooms had detection only, so the fire could not be attacked at its source. [BEA-RI report, via Wikipedia fr]
  • Reference #7 · news“OVH has chosen not to equip any of the five buildings in its Strasbourg data center with an automatic fire protection system.”
  • Sequence of events #3“ont parfaitement joue leur role”
  • Sequence of events #14~02h00 — Generalized flashover of SBG2; upper-floor temperature sensors saturate.
  • Reference #1 · regulatory“il n'y avait pas de systeme d'extinction automatise sur SBG2”

Reproduce: TIA-942 checklist · Tier advisor

FM-03 The free-cooling envelope lets fire and smoke climb vertically at high speed, and passive barriers are degradedSBG2 building envelope and compartmentation 9·5·6 270 —
Function
Hold a fire and its smoke inside the compartment of origin and away from neighbouring buildings
Effect
Smoke reaches all floors in about 15 minutes; the whole six-level building is lost; fire spreads to SBG1 (4 of 12 rooms lost) and reaches SBG3, whose 2-hour firewall is weakened by fire-stop doors held open
Cause
Raw-wood intumescent-treated floors, single-skin aluminium-blade cladding and high air permeability chosen for free-cooling airflow; battery charge rooms not meeting the required 2-hour fire resistance; fire-stop doors held open during evacuation
Prevention in place
Intumescent treatment of floors; a 2-hour firewall to SBG3
Detection in place
Aspirating detectors registered smoke on every floor within about 15 minutes, which shows the spread but could not stop it
S 9
This mode decides how far beyond the room the fire goes, and it took a whole building plus part of a second. Scored 9 rather than 10 because the facility loss is already carried at 10 by FM-01 and FM-02 and is not counted a third time at full weight.
O 5
The envelope is a standing condition present whenever a fire starts, which is infrequent; held at 5 like FM-02.
D 6
The detectors saw the spread as it happened: 'detected at onset, not prevented'.

Corrective action

  • Rebuild with proper fire-behaviour construction (BEA-RI lesson; no status recorded) Improvement #1
  • Treat the whole charging workshop as the regulated fire unit and design its compartmentation accordingly (no status recorded) Improvement #4

Who acts — playbook

Prevent
  • Safety officer Treat batteries and their chargers as one fire unit and compartment itImprovement #4
Detect
  • First responder Report smoke on upper floors as fire spread, not as a separate alarmNFPA 72
Contain
  • Fire & rescue commander Switch to defending the neighbouring buildings once the origin building cannot be heldNFPA 1561
  • Safety officer Close fire-stop doors behind the evacuation; never leave them wedged openContributing factor #7
Recover
  • Crisis lead Audit every site for fire vulnerability and carry the findings into rebuild standardsImprovement #6

Evidence

  • Contributing factor #4Free-cooling building design - raw-wood floors with intumescent treatment, single-skin aluminium-blade cladding, high air permeability - let fire and smoke climb vertically extremely fast; aspirating detectors sensed smoke on all floors within ~15 minutes. [BEA-RI report, free-cooling airflow confirmed via Wikipedia fr]
  • Contributing factor #7Degraded passive protection: fire-stop doors were held open during evacuation, and the battery charge rooms did not meet the 2-hour fire resistance required under the 29/05/2000 arrete (rubric 2925). [BEA-RI report]
  • Sequence of events #18~02h30-03h00 — Fire spreads to SBG1 (container-type build, losing 4 of 12 rooms) and SBG3 (protected by a 2-hour firewall, though fire-stop doors were held open, degrading it).
  • Metric #7Building loss: SBG2 (6-level) total loss; SBG1 partially damaged (4 of 12 rooms per BEA-RI); SBG3/SBG4 intact
  • Root cause“made the building extremely permeable to air and smoke and let fire climb vertically at high speed”
FM-07 A second fire breaks out in a battery room of SBG1SBG1 battery room during recovery 6·4·8 192 —
Function
Stay safe while the campus is being recovered
Effect
A fresh site power-down on 19 March delays recovery
Cause
Not recorded in the dossier
Prevention in place
None recorded
Detection in place
Not recorded in the dossier
S 6
It delayed restoration on a campus already out of service; no further loss is recorded, so 'partial outage confined to one zone'.
O 4
A second battery-room fire nine days later is an unusual combination, scored 'infrequent'; its cause is not in the dossier.
D 8
The dossier records only that the fire occurred and forced a power-down, so no pre-impact detection can be credited: scored 8.

Corrective action

  • Run a fleet-wide fire-vulnerability audit of all facilities (BEA-RI lesson; no status recorded) Improvement #6

Who acts — playbook

Prevent
  • Authorised electrical person Inspect and isolate surviving battery rooms before anything is re-energisedNFPA 855
Detect
  • First responder Keep a fire watch on battery rooms for the whole recoveryNFPA 855
Contain
  • Fire & rescue commander Treat the recovering site as a live fire risk until the batteries are clearedNFPA 1561
Recover
  • Incident commander Re-plan the restoration after the second power-downNIMS / ICS

Evidence

  • Sequence of events #2319 Mar 2021 — A second fire breaks out in a battery room of SBG1 ('un nouvel incendie a lieu dans un local a batteries du batiment SBG1'), forcing a fresh site power-down and delaying recovery.
  • Reference #5 · press“un nouvel incendie a lieu dans un local a batteries du batiment SBG1”
FM-08 Staff exposed to smoke, fire or live electrical equipmentNight crew and evacuation 10·2·2 40 —
Function
Get every person out of the building before the fire reaches them
Effect
Did not occur: the night crew was evacuated by 00h39 with zero fatalities and zero injuries
Cause
An energy-room fire in an occupied building
Prevention in place
Smoke detection and alarm to the security PC; evacuation procedure
Detection in place
First alarm at 00h35; guard at the room at 00h37; building evacuated at 00h39
S 10
Hazard to people is the rubric's 10 by definition, even though no one was hurt here.
O 2
Exposure needs the fire to outrun evacuation; with a small crew and fast alarm that is 'remote'.
D 2
Detection reached the security PC at ignition and evacuation took four minutes; the dossier credits detection with exactly this, so close to 'almost certainly stops it'.

Corrective action

  • None published — residual risk.

Who acts — playbook

Prevent
  • Safety officer Drill night evacuation with the real night staffingUptime OS
Detect
  • First responder Investigate an alarm in pairs and withdraw on visible smokeNFPA 1561
Contain
  • Fire & rescue commander Take the head count from the site before sending crews insideNFPA 1561
  • Safety officer Account for everyone at the assembly point and report the count to the fire serviceNIMS / ICS
Recover
  • Safety officer Keep staff out of live or smoke-damaged buildings until releasedNFPA 70E

On the record at this failure

  • Safety officer Evacuates SBG2 and accounts for the night crew: no victims, no injuries

Evidence

  • Sequence of events #500h39 — SBG2 evacuated; the small night crew is accounted for - zero victims, zero injuries.
  • Metric #6Personnel / casualties: night crew evacuated safely; 0 fatalities, 0 injuries
  • Sequence of events #300h35 — Near-simultaneous electrical faults strike the lead-acid batteries AND inverter ASI2 in two separate ground-floor energy rooms; first fire alarm reaches the site security PC. Optical and aspirating detectors 'ont parfaitement joue leur role'.
  • Technical deep-dive“Detection is credited ONLY with enabling safe evacuation, never suppression.”
Scoring rubric and method

Scales adapted from IEC 60812:2018 and AIAG-VDA. RPN = S × O × D. High: S ≥ 9 with O ≥ 4 or D ≥ 7, or RPN ≥ 300. Medium: RPN ≥ 120 or S ≥ 7. Severity overrides the product: 9 × 2 × 9 = 162 would otherwise hide a region-wide outage nothing could catch. Quotes are checked verbatim against this dossier; a revised score needs a published action. RZ analyst assessment, not an operator document.

Severity

10Hazard to people, or loss of the facility / several regions
9Region-wide or provider-wide outage of a foundational service, no workaround
8Full outage of a major service for hours
7Major degradation of a major service
6Partial outage confined to one zone or one service
5Customer-visible degradation
4Limited customer impact
3Internal impact only
2Negligible
1No effect

Occurrence

10Near certain: the cause is present in normal operation
8Frequent: routine work exercises the cause
6Occasional: a foreseeable slip or condition, weakly guarded
4Infrequent: needs an unusual combination
2Remote: guarded by design
1Eliminated by design

Detection

10No control could detect it
9Detected only through customer impact
8Detected after impact by internal monitoring
6Detected at onset, not prevented
4Detected before impact with time to act
2Automated interlock almost certainly stops it
1Certain to be stopped

Reproduce in a calculator

The links below open a calculator with the conditions this record states. Only the inputs listed here come from the record. Every other input is the baseline named under each link.

TIA-942 checklist

FMEA mode FM-02 · Tier 3 list, Enterprise

  • Automatic fire suppressionIn the record: not presentBaseline: ticked
    • Reference #3 · regulatory“equipped with fire detection but had no automatic extinguishing system”
    • Reference #7 · news“OVH has chosen not to equip any of the five buildings in its Strasbourg data center with an automatic fire protection system.”
  • Clean agent (FM-200/Novec 1230)In the record: not presentBaseline: ticked
  • Pre-action sprinkler systemIn the record: not presentBaseline: ticked
  • VESDA/smoke detection systemIn the record: presentBaseline: ticked

Baseline: every other item on the Tier 3, Enterprise list is ticked, so the gaps the checklist shows are the ones the record states. The baseline is part of this reproduction, not a claim about the site.

Open the checklist with these inputs

Tier advisor

FMEA mode FM-02 · the advisor's own defaults

  • Fire SuppressionIn the record: NoneBaseline: Pre-Action
    • Reference #3 · regulatory“equipped with fire detection but had no automatic extinguishing system”
    • Reference #7 · news“OVH has chosen not to equip any of the five buildings in its Strasbourg data center with an automatic fire protection system.”

Baseline: every other input keeps the tier advisor's default.

Open the tier advisor with these inputs

Root cause and contributing factors

The fire ignited at approximately 00h35 on 10 March 2021 from near-simultaneous electrical faults inside TWO separate ground-floor "salles energie" (energy rooms) of the six-level SBG2 building: a fault on the LEAD-ACID backup batteries in the battery room, and a fault on an inverter/UPS designated "ASI2" (alimentation sans interruption) in the adjacent inverter room.
Full root-cause narrative
A critical design detail per BEA-RI is that the inverter and its associated batteries were NOT in the same room ("l'onduleur et les batteries associees n'etaient pas dans la meme salle"). The battery bank was lead-acid (plomb): SBG2 held roughly 800 batteries of about 30 kg each. The report notes lead-acid chemistry is comparatively robust and internal short-circuits are rare on it, which is part of why the near-simultaneous dual departure is anomalous. The PRECISE failure mechanism was NOT established by BEA-RI, which explicitly deferred it to a pending judicial expertise ("Les causes precises des departs ... ne sont pas connues a la date du rapport"). The report lists candidate mechanisms for the ASI2 failure: (1) presence of liquid or humidity from the cooling system situated nearby, causing an internal short-circuit; (2) a malfunction linked to the maintenance intervention carried out that very morning; (3) operation of the inverter outside its normal operating ranges. Supporting the humidity hypothesis, ambient sensors on the rear of the inverters logged an anomalous humidity spike around 23h15 and a further marked rise just after 00h30, followed by continuous temperature rise and a new humidity peak at the moment of ASI2 failure. DISCLOSED EQUIPMENT UNCERTAINTY: the report does NOT name the UPS manufacturer, model or age, referring only to "l'equipementier qui a fourni les ASI." No abnormal grid event was recorded that night by Strasbourg Electricite Reseaux, ruling out an external electrical disturbance as the trigger. The LATENT root cause is design and defence-in-depth, not the ignition alone. First, OVH chose to equip NONE of the five SBG buildings with any automatic fire-suppression system ("OVH a choisi de n'equiper aucun des cinq batiments ... de systeme de protection incendie automatique") - the energy rooms had detection only. Second, the SBG2 construction - steel frame with prefabricated concrete cassettes, raw-wood floors with intumescent treatment, and single-skin aluminium-blade cladding designed for free-cooling airflow - made the building extremely permeable to air and smoke and let fire climb vertically at high speed. Third, the site had NO readily accessible general electrical cut-off, so the building could not be made safe until roughly 02h30, long after suppression water was needed. Fourth, the on-site fire-water provision was a single public hydrant delivering under 60 m3/h with no owned water reserve or pumping means from the Rhine canal. The MAINTENANCE thread is a documented contributing hypothesis, not a proven cause. ASI2 had undergone maintenance in the days before, and again the morning of the fire, "en raison de problemes recurrents de passage en mode by-pass inexpliques" (recurring, unexplained by-pass-mode trips). The maintenance and return-to-service reports "ne mentionnent aucun element singulier." Compounding this, the lead-acid batteries had NO condition monitoring ("Les batteries ne sont pas equipees de systeme de scrutation ou de supervision"), and OVH could not produce the inverters' operating parameters at the moment of failure ("OVH nous a indique ne pas en disposer"). Recurring unexplained faults on a critical inverter, a same-morning intervention, and the absence of battery/UPS telemetry together form the latent maintenance-and-monitoring gap, even though BEA-RI stopped short of formal causation.

Contributing factors by category

Contributing factors by category — OVHcloudEquipment: Inverter ASI2 fault; Battery bank fault; Generators auto-restart. Design: No automatic suppression; Combustible free-cool shell; UPS and batteries split. Process: By-pass trips not traced; No general cut-off; Fire-stop doors held open. Environment: One hydrant, under 60 m3/h. External: No off-site customer backup. Effect: SBG2 destroyed, 3.6M sites offline.SBG2 destroyed, 3.6M sites offlineEquipmentInverter ASI2 faultBattery bank faultGenerators auto-restartProcessBy-pass trips not tracedNo general cut-offFire-stop doors held openExternalNo off-site customer backupDesignNo automatic suppressionCombustible free-cool shellUPS and batteries splitEnvironmentOne hydrant, under 60 m3/h
Each short label stands for a contributing factor or failure mode recorded in this dossier; the full sentences are listed below.
  • No automatic fire-suppression system in ANY of the five SBG buildings (no sprinkler, water mist, or gas inerting) - a deliberate design choice per BEA-RI; the energy rooms had detection only, so the fire could not be attacked at its source. [BEA-RI report, via Wikipedia fr]
  • Absence of a readily accessible general site electrical cut-off: isolation required tripping the upstream source substation because client-owned HT posts sat inside the fire zone and could not be operated, delaying safe de-energisation from the ~00h58 cut order to ~02h30. [BEA-RI report]
  • MAINTENANCE / MONITORING GAP: the faulted inverter ASI2 had recurring, unexplained by-pass-mode trips and was serviced the very morning of the fire; the lead-acid batteries had NO scrutation/supervision, and OVH could not produce the inverters' operating parameters at the moment of failure. [BEA-RI report]
  • Free-cooling building design - raw-wood floors with intumescent treatment, single-skin aluminium-blade cladding, high air permeability - let fire and smoke climb vertically extremely fast; aspirating detectors sensed smoke on all floors within ~15 minutes. [BEA-RI report, free-cooling airflow confirmed via Wikipedia fr]
  • Grossly insufficient fire-water: a single public hydrant delivering under 60 m3/h, with no owned water reserve and no pumping means from the Rhine canal, forcing reliance on the fireboat EUROPA. [BEA-RI report]
  • Diesel generators slaved to supply continuity auto-started despite the fire and had to be manually neutralized to keep them from restarting on the cut, prolonging the live-electrical condition. [BEA-RI report]
  • Degraded passive protection: fire-stop doors were held open during evacuation, and the battery charge rooms did not meet the 2-hour fire resistance required under the 29/05/2000 arrete (rubric 2925). [BEA-RI report]
  • UPS and its associated batteries were located in DIFFERENT rooms, and two near-simultaneous departures occurred across both spaces, complicating any single-point containment. [BEA-RI report]
  • Customer-side resilience gap: many customers had no off-site/geo-redundant backup, so the SBG2 total loss destroyed both primary data and the only copies for those customers. [Wikipedia en]

Analysis

An ignition that was never fully explained - and did not need to be

BEA-RI is unusually candid that the precise mechanism of the near-simultaneous ASI2/battery faults was not established and was left to judicial expertise. The forensic weight therefore falls not on the spark but on why a spark in one ground-floor energy room became a total loss of a six-storey building and spread to two neighbours. The report's own hypotheses (cooling-system humidity, the same-morning maintenance, out-of-range inverter operation) are presented as candidates, not conclusions, and the equipment maker/model is deliberately unnamed. Any narrative that asserts a definitive electrical cause overstates the evidence.

The suppression void is the decisive finding

The single most consequential fact is that none of the five SBG buildings had any automatic fire suppression - a design choice, not an oversight. Detection performed flawlessly and saved every life, but detection without suppression only enables evacuation. With no sprinkler, mist or gas system, the only defence was hand extinguishers and the public water network, which was itself grossly undersized. This is the lever that would most plausibly have changed the outcome.

De-energisation as the true bottleneck

Even once firefighters were on scene, they could not commit water at scale because the building stayed live. No accessible general cut-off, client HT posts trapped inside the fire zone, generators auto-restarting on continuity logic, and ~20 minutes of residual lead-acid supply combined to keep current flowing until ~03h28. Flashover (~02h00) beat the safe-to-attack moment (~02h30). The electrical architecture, not firefighter effort, dictated the timeline.

Building physics engineered for cooling, not containment

Free-cooling drove the envelope design - high air permeability, ventilated single-skin cladding, raw-wood (intumescent-treated) floors - which is efficient thermally but carried smoke to every floor within ~15 minutes and gave fire a vertical chimney. Passive protection that should have compartmentalised (2-hour battery-room rating, fire-stop doors) was degraded in practice, with doors held open during evacuation. The same feature that made the DC efficient made it burn.

Blast radius and the limits of legal recourse

Netcraft measured ~3.6 million websites and 464,000 domains dropping offline; customers who relied solely on SBG2, including in-facility backups, lost data outright. Yet the litigation arc is a cautionary tale: first-instance awards of ~EUR100k and ~EUR145k to two customers in 2023 were largely gutted on appeal (2025-2026) under OVH's contractual liability caps, leaving token sums. The practical lesson for customers was self-provisioned geo-redundancy, because neither the facility nor the contract would make them whole.

Technical deep-dive
The forensic core is a defence-in-depth failure layered on an unestablished electrical ignition. DETECTION was present and effective but suppression-blind: the energy rooms carried automatic optical point smoke detectors PLUS aspirating (VESDA-type) smoke detection PLUS manual call points, and BEA-RI credits them ("Ces derniers ont parfaitement joue leur role de detection"). The first alarm reached the site security PC at 00h35; the guard reached ground-floor energy room no.2 at 00h37 and found thick black smoke; the building was evacuated by 00h39. The aspirating detectors sensed smoke on ALL floors within ~15 minutes, evidence of "une grande permeabilite du batiment a l'air exterieur et donc aux fumees." Detection is credited ONLY with enabling safe evacuation, never suppression. SUPPRESSION was ABSENT - the central finding. No gas inerting, no water mist, no sprinkler existed in any SBG building. BEA-RI stresses an automatic system would have applied water very early "sans meme attendre l'arret de la fourniture d'electricite, et sans exposer de personnel a un risque d'electrocution." With none present, the only site defence was trained staff with hand extinguishers plus the public network - one supply line, one hydrant under 60 m3/h. The DE-ENERGISATION delay is the mechanism that turned a contained ignition into a total-loss conflagration. The cut order was given ~00h58, but four factors prevented a safe electrical death of the building until ~02h30: (1) no easily accessible general site cut-off, so isolation required tripping the upstream source substation; (2) client-owned HT posts sat inside the firefighters' intervention zone and could not be operated - SER cut remotely at the source substation, effective ~01h50; (3) diesel generators, slaved to supply continuity, auto-started despite the fire and had to be neutralized manually; (4) charged lead-acid batteries were the last live source, giving ~20 minutes of residual supply. Result: at 02h14 there was STILL current in the fully-ablaze building 2, and only "a partir de 03h28, il n'y a plus de courant sur le site." Firefighters observed "des arcs electriques dans le local energie" and could not engage massive water until the electrical risk cleared (~02h30) - by which point SBG2 had reached generalized flashover (~02h00) and was spreading to SBG1 and SBG3. The fireboat EUROPA (providing 3 pumps at 15,000 L/min and 2 foam/water lances at 4,500 L/min each), requested at ~01h49 and on-scene at ~02h57, was described as decisive in sparing SBG1/SBG3 from worse loss; ~4000 L of foam concentrate were consumed. SBG3's 2-hour firewall held better, but firefighters reported fire-stop doors held open during evacuation, degrading it; the battery charge rooms that should have met 2-hour fire resistance under the 29/05/2000 arrete (rubric 2925) did not. NOTE: the granular BEA-RI-attributed times, flows and equipment figures in this section could not be independently re-verified this pass because the BEA-RI report host was unreachable; they rest on the report's attribution and are internally consistent, but are not corroborated by a second accessed source.

Corrective actions and lessons

Correction of errors

ActionOwnerStatus
Fit automatic fire-suppression to all energy/battery rooms and datahalls across the SBG estate and rebuildOVHcloud (facilities/safety)Committed post-incident per public statements; independent completion not verified in this review
Provide accessible general electrical cut-off and separate UPS from associated batteries into fire-rated roomsOVHcloud (electrical engineering)BEA-RI recommendation; implementation status unverified
Add UPS/battery supervision and operating-parameter logging; RCA recurring ASI by-pass trips before return-to-serviceOVHcloud (maintenance/M&O)BEA-RI lesson; status unverified
Provision owned fire-water reserves/pumping sized to site (Rhine canal) beyond the single public hydrantOVHcloud + SDIS 67BEA-RI recommendation; status unverified
Publish and complete the BEA-RI technical investigation and cooperate with judicial expertise on precise ignition causeBEA-RI / judicial expertBEA-RI report published 27 May 2022; precise cause deferred to judicial expertise
Advise/enable customers on geo-redundant backups (default off-site backup offering)OVHcloud (product)Backup offerings expanded post-incident per public messaging; not verified here

Lessons learnt

  • Fire detection without automatic suppression buys almost no containment time in a data center — SBG2 rooms had detection but no extinguishing system, and water could not be applied early without first cutting power.
  • The battery-charging chain, not just the battery room, is the true hazard unit; the UPS and its batteries were in separate rooms and the fault spanned both, so single-room protection would not have prevented the fire.
  • Energy-efficient free-cooling construction (combustible raw-wood floors, single-skin cladding) trades fire compartmentation for airflow — the same design that cuts cooling energy accelerated vertical fire spread.
  • A facility must be de-energisable quickly and locally; relying on an upstream substation cut left the building live for over an hour, blocking safe massive water application while the fire grew.
  • On-site water resilience matters — a single hydrant below 60 m3/h with no reserve and no canal-pumping capability forced dependence on an external fireboat that arrived roughly two hours into the incident.
  • Preventive battery monitoring (operating conditions and state, per manufacturer rules, with BMS at scale) is essential observability; the exact fault cause could not be determined afterward.
  • A total-loss fire is a plausible, not far-fetched, scenario for a data center and must be planned for by both operators and local emergency services.

Improvements

  • Rebuild energy rooms and buildings with automatic fire suppression and proper fire-behaviour construction, incorporating SBG2 feedback into detection, firefighting means, and emergency procedures.
  • Install an easily accessible general site cut-off and drill electrical-securing procedures so responders can safely deploy water within minutes rather than hours.
  • Provide on-site extinguishing-water reserves and/or canal-pumping capability sized for a widespread-fire scenario, and ensure ICPE water-resource requirements are met.
  • Treat the whole charging workshop (batteries plus charging equipment) as the regulated fire unit and design its compartmentation accordingly.
  • Deploy battery monitoring / BMS with manufacturer-based preventive-maintenance and replacement rules across large battery fleets.
  • Run a fleet-wide fire-vulnerability audit of all facilities and feed findings into rebuild standards.
  • Advance professional fire-safety guides and ANSSI certification for data centers instead of ICPE classification, reflecting that the dominant consequence is economic/strategic (data loss and service unavailability) rather than human or environmental.

References and provenance

Quotes are short, attributed, and for provenance only; the analysis is original. Last verified 2026-07-31.

Root access required

The DC Incidents dossier is a root-only module. Sign in with an authorized account to continue.

Back to Home