NIRS Daejeon Government Data Center: UPS Lithium-Ion Battery Fire During Relocation Work
On the evening of 26 September 2025, a lithium-ion UPS battery that had been disconnected in order to be relocated to the basement of the NIRS Daejeon government data center entered thermal runaway and exploded in a server room, igniting a fire that took roughly ten hours to extinguish. When the fire broke out, all 647 government IT systems at the Daejeon headquarters were taken offline (96 of them directly destroyed, the rest shut down as a precautionary safety measure). Core national services including digital IDs, Korea Post postal banking, emergency GPS tracking, courts and tax were paralyzed, and all documents on the G-Drive cloud used by up to 30 ministries and nearly 191,000 employees were permanently lost because the repository was not backed up externally. Recovery reached 70.5 percent by 24 October and later exceeded 95 percent; the NIRS chief and three other officials were booked for causing the fire through on-duty negligence, the chief was relieved of duty, and Daejeon police raided NIRS.
Failure cascade
Trigger → primary fault → downstream blast radius, derived from the sourced root cause and affected-services record.
Facility & location
- Operator
- National Information Resources Service (NIRS)
- Data center
- NIRS Daejeon National Information Resources Service (government data center)
- Location
- Daejeon, South Korea
- Date
- 2025-09-26
Impact & scale
- Users affected
- Nearly 191,000 civil servants (out of 750,000 public-sector officials nationwide) had access to the affected G-Drive cloud as of August 2025; nationwide citizen impact via digital IDs, postal banking, emergency GPS tracking, courts and tax systems
- Financial
- Not publicly quantified in reachable primary reporting; includes irrecoverable, permanent loss of all G-Drive documents for up to 30 ministries
- Scope
- Catastrophic (national government infrastructure)
- 647 government IT systems taken offline
- 96 systems directly destroyed
- 709 government services disrupted
- Digital ID / mobile identity
- Korea Post postal banking
- Korea Post mail delivery
- Emergency GPS tracking
- Court systems
- Tax systems
- Document 24 (online government document service)
- G-Drive government cloud (up to 30 ministries)
Impact data & metrics
| Systems powered off at Daejeon HQ | 647 systems |
| Government online services interrupted | ~96 services |
| Time to initial knockdown (초진) | >10 hours |
| Fire casualties | 1 worker (1st-degree burns, face/arm) |
| Battery modules in thermal-runaway cascade | 384 modules (press-derived) |
| Battery age vs recommended life | ~11 years (installed Aug 2014) vs ~10-yr recommended (press-derived) |
| Time to full extinguishment after ignition | ~22 hours (press-derived) |
| Permanent data loss (G-Drive, no backup) | ~858 TB (press-derived) |
| Government officials whose data was lost | ~125,000 (press-derived) |
| Systems restored mid-recovery | ~231 systems (~32.5%) (press-derived) |
| Negligence charges filed | 5 charged (press-derived) |
| Firefighting resources deployed | ~101 firefighters, ~31 apparatus (press-derived) |
Magnitude profile
Blast radius scored maximal: 647 systems offline, 96 destroyed, 709 services disrupted, and G-Drive data for up to 30 ministries permanently lost. Users score reflects both ~191,000 employees with G-Drive access and nationwide citizen exposure across digital ID, postal banking, courts and tax. Duration scored high because although the physical fire lasted ~10 hours, service recovery stretched for weeks (70.5% by Oct 24, >95% later). Financial score is high-but-unconfirmed: no KRW/USD loss figure is published in reachable primary sources, but the permanent, unrecoverable loss of an entire multi-ministry document repository represents severe realized damage.
Sequence of events (SOE)
- TRIGGER UPS lithium-ion battery bank (reported LG Energy Solution, 384 modules) installed at NIRS Daejeon 5th-floor server/UPS room — the asset that later failed (press-derived, single-source secondary, unverified at review)
- TRIGGER Battery bank reportedly passes its last safety inspection despite being past its ~10-year recommended service life (press-derived secondary, unverified at review)
- TRIGGER Worker switches OFF the UPS lithium-ion battery power to begin disconnection for relocation from the 5th floor to the basement — ~40 min before ignition, derived from the verified 20:20 timestamp
- DETECTION First fire report from the 5th-floor server room (human-noticed; no automated detection-alarm time or battery off-gas early-warning disclosed in any source)
- CASCADE Sparks fly from the battery for an 'unknown reason' (미상의 이유); thermal runaway/explosion ignites the fire; one worker suffers 1st-degree burns to face and arm
- CASCADE Single-cell failure reportedly cascades runaway through all 384 modules; self-oxidising chemistry drives repeated re-ignition; peak reported >160°C (press-derived secondary)
- MITIGATION Fire authorities dispatch immediately — reported ~101 firefighters and ~31 apparatus; an ~20-person task force including lithium-battery experts formed (press-derived secondary)
- MITIGATION Crews constrained from water flooding to avoid destroying the protected servers ('데이터를 보관하는 장비의 손상 우려'); rely on gas/CO2, which cannot arrest the self-oxidising runaway
- MITIGATION NIRS cuts power to all 647 Daejeon systems — protective mass shutdown as the room's HVAC/CRAC (항온항습장치) is lost, risking server overheating
- IMPACT Government online services degrade: approximately 96 government online services interrupted (mobile ID/Government24 auth and related public services)
- MITIGATION Initial knockdown reached only after over 10 hours ('초진까지 10시간 이상이 소요'), delayed by the water constraints on the lithium-ion fire
- RECOVERY Fire reportedly fully extinguished ~22 hours after ignition, following repeated re-ignition characteristic of thermal runaway (press-derived secondary)
- IMPACT Authorities reportedly confirm ~858 TB of G-Drive data lost with NO backup; the drive held data for ~125,000 government officials (press-derived, not re-verified at review)
- IMPACT Scope reported as widening: hundreds of public-institution systems taken offline; G-Drive cited as the destroyed system without recoverable backup (press-derived)
- CASCADE A senior officer of the Digital Government Innovation Office overseeing restoration reportedly dies after a fall near the Sejong complex; ministry reviews possible overwork — NOT a fire casualty (press-derived, not re-verified)
- RECOVERY Recovery proceeds with a reported ~32.5% (231 systems) restored; ministries report operations badly disrupted where work materials lived only on G-Drive (press-derived)
- RESTORED South Korean police reportedly charge five with professional negligence: one NIRS official, one PM-firm employee, three construction workers; unqualified crew and illegal subcontracting cited (press-derived, not re-verified)
- RESTORED Final determination of the exact battery-failure cause reported as expected; formal investigation ongoing (press-derived)
Root cause
Contributing factors
- Unqualified, inexperienced personnel performing the Li-ion relocation: police reportedly found the crew had no experience with large-scale battery relocations and deemed them unqualified (Anadolu, press-derived, not re-verified at review).
- Illegal subcontracting of the relocation work reportedly broke the qualification/accountability chain (Anadolu, press-derived).
- Safety protocol not followed during disconnection — plausibly disconnecting wiring before the pack was fully de-energised, producing an arc/voltage spike; ko.wikipedia (verified) labels the spark cause 'unknown,' and the arc hypothesis is secondary (breached.company).
- Aged asset kept in service and physically relocated rather than retired: reported as an LG Energy Solution bank installed August 2014, ~11 years old and past ~10-year recommended life (breached.company, single-source secondary, unverified at review).
- No battery backup for the ~858 TB G-Drive ('couldn't have a backup system due to its large capacity') — a disaster-recovery governance failure that converted a contained fire into permanent data loss for ~125,000 officials (Anadolu/DCD, press-derived).
- Physical siting of a volatile Li-ion bank close to production servers with inadequate fire separation, exposing adjacent racks to runaway heat and smoke (breached.company, secondary).
- Suppression regime mismatched to chemistry: server-hall water-cautious firefighting could not arrest a self-oxidising Li-ion runaway, driving the verified >10h initial knockdown (ko.wikipedia).
- Loss of HVAC/CRAC (항온항습장치) forced a protective mass power-down of 647 systems, widening the outage well beyond the fire's footprint (ko.wikipedia, verified).
- No disclosed battery-level off-gas/thermal-runaway early-warning detection; the event was human-noticed at ~20:15 rather than caught at cell venting (ko.wikipedia, verified).
Correction of errors (COE)
- Retire and safely dispose of all UPS lithium-ion battery banks at/before end of recommended service life; ban physical relocation of past-life packs; require certified crews and verified full de-energisation before any disconnection.
- Provision real backup and geographically separate disaster recovery for all critical government stores including G-Drive, removing the 'too large to back up' exemption.
- Install battery-level off-gas and thermal-runaway early-warning detection and rated fire separation between Li-ion energy storage and production server halls.
- Prohibit illegal subcontracting on critical-infrastructure work; enforce contractor qualification verification and safety-protocol sign-off for energy-storage handling.
- Adopt Li-ion-appropriate fire response doctrine (immersion/copious-water cooling capability) and pre-plan power/cooling failure domains to bound outage blast radius.
- Complete formal cause investigation and publish findings; resolve the 5 negligence charges through the courts.
Lessons learnt
- A single-rack lithium-ion event defines its blast radius through shared power and cooling, not flame footprint: the 647-system outage came from the deliberate mass power-down and lost HVAC/CRAC as much as from the fire itself (ko.wikipedia, verified).
- Server-hall fire doctrine is incompatible with Li-ion chemistry: water-cautious tactics could not arrest a self-oxidising runaway, producing the verified >10h initial knockdown (ko.wikipedia) and reportedly ~22h to full out with repeated re-ignition (breached.company). The one effective tactic — copious water/immersion cooling — is the one the room's mission forbids.
- 'Too big to back up' is a decision, not a fact: ~858 TB was reportedly lost solely because G-Drive had no backup 'due to its large capacity' (Anadolu/DCD). Storage cost is always cheaper than total sovereign data loss.
- A passed safety inspection is not proof of battery health: a reportedly passed June 2025 inspection preceded catastrophic runaway (breached.company); pass/fail inspection without cell-level off-gas/impedance/thermal diagnostics gives false assurance.
- Human factors dominate: the fire is attributed to a disconnection during relocation with the ignition officially 'unknown' (ko.wikipedia) and police reportedly citing unqualified crew and illegal subcontracting (Anadolu) — governance of who touches energy storage matters as much as the hardware.
- Cascade risk extends beyond the fire: recovery pressure was severe enough that an official overseeing restoration reportedly died amid overwork concerns (techspot) — recovery staffing and welfare must be planned, not improvised.
Improvements & remediation
- Mandate hazardous-work permits, verified de-energization, thermal monitoring and physical isolation for all lithium-ion battery relocation and decommissioning, removing live server rooms from the work zone.
- Relocate lithium-ion UPS energy storage into dedicated fire-rated battery rooms with early-warning gas/thermal detection and battery-appropriate suppression, separated from IT space.
- Provision isolated, tested, recoverable backups and cross-site replication for shared government cloud repositories so no single fire can cause permanent multi-ministry data loss.
- Distribute and geo-replicate critical national services across multiple facilities/availability zones to eliminate single-facility, single-event nationwide paralysis.
- Compartmentalize and fault-isolate the facility (fire zoning, independent power and cooling per hall) so that a fire in one room does not require a precautionary shutdown of the entire co-located estate.
- Institutionalize a pre-defined, drilled restoration runbook with priority tiers (Grade-1 services, cooling-first sequencing) and transparent progress reporting.
Comprehensive analysis
What happened (verified core)
On the evening of 2025-09-26, during relocation work on a UPS lithium-ion battery in the 5th-floor server/UPS room of the NIRS Daejeon government data center, a worker switched the battery power off and about 40 minutes later, at ~20:20 KST, sparks flew from the battery 'for an unknown reason' and a fire broke out (ko.wikipedia, verified verbatim). A first report came at ~20:15. NIRS powered off all 647 Daejeon systems as the room's HVAC/CRAC failed, and roughly 96 government online services were interrupted. Water suppression was constrained by fear of destroying the data-storage equipment, so initial knockdown took over 10 hours. One worker suffered 1st-degree burns.
Why it became a disaster (governance amplifiers)
The physical fire was contained to a room, but the impact was national. Press reporting (Anadolu/DCD, not re-verifiable at review) states the ~858 TB G-Drive store — data for ~125,000 officials — had no backup 'due to its large capacity,' making its loss permanent, while other destroyed systems were recoverable. Police reportedly charged five people (an NIRS official, a PM-firm employee, three construction workers) with professional negligence, citing an unqualified, inexperienced crew and illegal subcontracting. The disaster scale was manufactured by DR governance, contractor governance, and asset-lifecycle failures, not by the battery alone.
The Li-ion suppression conflict
Lithium-ion thermal runaway is self-oxidising, so clean-agent and water-cautious server-hall firefighting cannot arrest it, and it propagates cell-to-cell. The only reliable tactic — immersion/copious-water cooling — is precisely what a server room forbids to protect equipment. This is the unresolved doctrinal conflict the incident exposes: the verified >10h knockdown (ko.wikipedia) and reportedly ~22h full-out with repeated re-ignition (breached.company, secondary) are the direct symptom. No battery-level off-gas or thermal-runaway early warning was disclosed; the fire was human-noticed, not caught at cell venting.
Sourcing and confidence
High-confidence, verified facts (ko.wikipedia, re-fetched at review): ignition ~20:20 with unknown spark cause, first report ~20:15, worker powered off battery ~40 min prior, 647 systems shut, HVAC/CRAC loss, water-suppression difficulty, >10h knockdown, ~96 services interrupted, 1 worker 1st-degree burns, presumed UPS lithium-battery cause. Press-derived and NOT re-verifiable at review (fetch 403/404, search budget exhausted): 858 TB, no-backup rationale, ~125,000 officials, 5 negligence charges, restoration %, and all breached.company technical specifics (LG Energy Solution, 384 modules, Aug-2014 install, ~60 cm siting, >160°C, ~22h, ~101 firefighters, June-2025 inspection). These are retained as attributed, hedged secondary claims, not established fact.
Technical deep-dive
References & provenance
- official-postmortem 행정안전부 장관, 국정자원 대구센터 방문 행정정보시스템 안전관리 등 현장 점검 (Ministry of the Interior and Safety press release, korea.kr government portal)“전산실 내 리튬이온 배터리의 안전 조치 (safety measures for lithium-ion batteries inside the server room)”https://www.korea.kr/briefing/pressReleaseView.do?newsId=156770075
- official-postmortem 민·관 협력 데이터센터 안전진단 (National Fire Agency / 소방청 press release, korea.kr government portal)“최근 대전 국가정보자원관리원 화재를 계기로 (prompted by the recent Daejeon NIRS fire)”https://www.korea.kr/briefing/pressReleaseView.do?newsId=156734578
- press Data recovery / 858 TB loss after South Korea government data center fire — Anadolu Agency“The G-Drive couldn't have a backup system due to its large capacity (as reported; ~858 TB, data for ~125,000 officials). NOTE: could not be re-fetched at review (403); rests on prior capture.”https://www.aa.com.tr/en/asia-pacific
- press South Korea government data center fire, 858 TB G-Drive lost — DataCenterDynamics“~858 TB G-Drive destroyed with no recoverable backup while other destroyed systems were recovered (as reported). NOTE: URL returned HTTP 403 at review; not independently re-verified.”https://www.datacenterdynamics.com/en/news/
- press Auxiliary power remained connected during South Korea data center fire, police believe (DataCenterDynamics)“though the main power to the building was disconnected when the fire broke out, an auxiliary power system connected to the data center's Uninterruptible Power Supply (UPS) battery backup system was not”https://www.datacenterdynamics.com/en/news/auxiliary-power-remained-connected-during-south-korea-data-center-fire-police-believe/
- press Five charged with professional negligence over South Korea govt data center fire (DataCenterDynamics)“Investigators said that workers failed to follow safety protocols, didn't use the required insulation materials, and failed to fully discharge the batteries before moving them, increasing the risk of fire.”https://www.datacenterdynamics.com/en/news/five-charged-with-professional-negligence-over-south-korea-govt-data-center-fire/
- press 858TB of government data may be lost for good after South Korea data center fire (DataCenterDynamics)“the drive was one of 96 systems completely destroyed in the fire, and there is no backup ... The G-Drive couldn't have a backup system due to its large capacity”https://www.datacenterdynamics.com/en/news/858tb-of-government-data-may-be-lost-for-good-after-south-korea-data-center-fire/
- press 국가정보자원관리원 화재 (Korean Wikipedia)“무정전 전원장치(UPS)용 리튬이온배터리 전원을 작업자가 끄고 약 40분 지난 오후 8시 20분경 미상의 이유로 배터리에서 불꽃이 튀며 화재가 발생”https://ko.wikipedia.org/wiki/국가정보자원관리원_화재
- news South Korea data center fire 'paralyzes' vital services“CNN reported the Daejeon government data center fire paralyzed vital public services.”https://www.cnn.com/2025/09/27/asia/south-korea-fire-data-center-daejeon-intl-hnk
- news Second data center in a week catches fire in Daejeon“DCD framed the event as the second data center in a week to catch fire in Daejeon.”https://www.datacenterdynamics.com/en/news/second-data-center-in-a-week-catches-fire-in-daejeon-south-korea/
- news Police raid NIRS offices over Daejeon data center fire“"Police raided the headquarters of the National Information Resources Service in Daejeon on Thursday morning to look into a Sept. 26 fire..." (Daejeon Metropolitan Police also searched three firms tied to the UPS system).”https://www.koreaherald.com/article/10588621
- news Fire authorities response and extinguish timeline (Korea Herald)“"Fire authorities received a report of a battery fire at the national data infrastructure center at 8:20 p.m. on Friday and deployed 101 firefighters and 31 fire vehicles... extinguished at 6:30 a.m., Saturday, around 10 hours after the initial report."”https://www.koreaherald.com/article/10601773
- news Ignition source and G-Drive data loss (Korea Herald)“"The source of the fire was later identified as an uninterruptible power supply battery that was disconnected in order to be relocated to the basement." The G-Drive "system was not backed up externally, all documents stored on the repository have been lost."”https://www.koreaherald.com/article/10588068
- news Root-cause corroboration and negligence booking (Korea Herald)“"An explosion of lithium-ion batteries in a server room has been cited as the main cause of the blaze... Lee and three other officials have been booked for causing a fire through negligence while on duty."”https://www.koreaherald.com/article/10626223
- news Restoration milestone, 70.5 percent (Korea Herald)“"500 out of 709 services disrupted by the fire... had been brought back online, marking a restoration rate of 70.5 percent... 34 out of 40 'Grade 1' services... have been restored."”https://www.koreaherald.com/article/10600976