← All incidents
Incident dossier · Rank #3 · magnitude 9.2

NIRS Daejeon Government Data Center: UPS Lithium-Ion Battery Fire During Relocation Work

National Information Resources Service (NIRS) 2025-09-26 restoration time not established FirePower

Summary

On the evening of 26 September 2025, a lithium-ion UPS battery that had been disconnected in order to be relocated to the basement of the NIRS Daejeon government data center entered thermal runaway and exploded in a server room, igniting a fire that took roughly ten hours to extinguish. When the fire broke out, all 647 government IT systems at the Daejeon headquarters were taken offline (96 of them directly destroyed, the rest shut down as a precautionary safety measure). Core national services including digital IDs, Korea Post postal banking, emergency GPS tracking, courts and tax were paralyzed, and all documents on the G-Drive cloud used by up to 30 ministries and nearly 191,000 employees were permanently lost because the repository was not backed up externally. Recovery reached 70.5 percent by 24 October and later exceeded 95 percent; the NIRS chief and three other officials were booked for causing the fire through on-duty negligence, the chief was relieved of duty, and Daejeon police raided NIRS.

Users affected
Nearly 191,000 civil servants (out of 750,000 public-sector officials nationwide) had access to the affected G-Drive cloud as of August 2025; nationwide citizen impact via digital IDs, postal banking, emergency GPS tracking, courts and tax systems
Duration
Fire ~20:20 KST 26 Sep; only 231 of 647 systems (~32.5%) restored weeks later.
Financial
Not publicly quantified in reachable primary reporting; includes irrecoverable, permanent loss of all G-Drive documents for up to 30 ministries
Scope
Catastrophic (national government infrastructure)
Site
NIRS Daejeon National Information Resources Service (government data center) · Daejeon, South Korea
Services down
647 government IT systems taken offline, 96 systems directly destroyed, 709 government services disrupted, Digital ID / mobile identity, Korea Post postal banking, Korea Post mail delivery, Emergency GPS tracking, Court systems, Tax systems, Document 24 (online government document service), G-Drive government cloud (up to 30 ministries)

How the defences failed

How the defences failed — NIRS Daejeon8 failure modes in the order the sequence of events first shows them, 0 latent conditions with no moment in the record, ending in the outcome: 647 systems offline · 858 TB lost.ACTIVE — IN THE ORDER THE RECORD SHOWS THEMFM-01 · RPN 540Li-ion bank runawayS10 · O6 · D9FM-02 · RPN 432Moved while live and chargedS9 · O6 · D8FM-04 · RPN 336No cell-level early warningS7 · O6 · D8FM-05 · RPN 288Water held back from Li-ionS8 · O6 · D6FM-06 · RPN 216One shutdown takes 647 systemsS9 · O4 · D6FM-08 · RPN 224Weeks-long restorationS7 · O4 · D8FM-07 · RPN 486G-Drive has no backupS9 · O6 · D9FM-03 · RPN 384Illegal subcontractingS8 · O6 · D8OUTCOME647 systems offline · 858 TB lostLEGENDHigh priorityMedium or low priorityNext failure in the record
How the defences failed — NIRS Daejeon8 failure modes in the order the sequence of events first shows them, 0 latent conditions with no moment in the record, ending in the outcome: 647 systems offline · 858 TB lost.ACTIVE — RECORD ORDERFM-01 · RPN 540Li-ion bank runawayS10 · O6 · D9FM-02 · RPN 432Moved while live and chargedS9 · O6 · D8FM-04 · RPN 336No cell-level early warningS7 · O6 · D8FM-05 · RPN 288Water held back from Li-ionS8 · O6 · D6FM-06 · RPN 216One shutdown takes 647 systemsS9 · O4 · D6FM-08 · RPN 224Weeks-long restorationS7 · O4 · D8FM-07 · RPN 486G-Drive has no backupS9 · O6 · D9FM-03 · RPN 384Illegal subcontractingS8 · O6 · D8OUTCOME647 systems offline · 858 TB lostLEGENDHigh priorityMedium or low priorityNext failure in the record
Every failure mode of the FMEA below. Active modes run in the order the sequence of events first shows them — record order, not a proof of cause; latent modes were in place before the event. Red outline: high priority. Dashed: no published corrective action.
Magnitude sub-scores (0–10)Magnitude sub-scores (0–10)Users 9Users affected (0–10) — breadth of the user/customer population impacted. — scored 9/10.Financial 8Financial impact (0–10) — direct + consequential cost. — scored 8/10.Duration 9Outage duration (0–10), from the measured duration by fixed bands: <1 h 3 · 1–4 h 4 · 4–12 h 5 · 12–24 h 6 · 1–3 d 7 · 3–7 d 8 · 7–30 d 9 · >30 d 10; no customer downtime 1. — scored 9/10.Blast 10Blast radius (0–10) — how wide the fault propagated across systems/regions. — scored 10/10.
Magnitude 9.2 = blast 10×0.35 + users 9×0.25 + financial 8×0.20 + duration 9×0.20 (sub-scores 0–10 · weighted composite)

Blast radius scored maximal: 647 systems offline, 96 destroyed, 709 services disrupted, and G-Drive data for up to 30 ministries permanently lost. Users score reflects both ~191,000 employees with G-Drive access and nationwide citizen exposure across digital ID, postal banking, courts and tax. Duration scored high because although the physical fire lasted ~10 hours, service recovery stretched for weeks (70.5% by Oct 24, >95% later). Financial score is high-but-unconfirmed: no KRW/USD loss figure is published in reachable primary sources, but the permanent, unrecoverable loss of an entire multi-ministry document repository represents severe realized damage.

All 12 impact metrics
Systems powered off at Daejeon HQ647 systems
Government online services interrupted~96 services
Time to initial knockdown (초진)>10 hours
Fire casualties1 worker (1st-degree burns, face/arm)
Battery modules in thermal-runaway cascade384 modules (press-derived)
Battery age vs recommended life~11 years (installed Aug 2014) vs ~10-yr recommended (press-derived)
Time to full extinguishment after ignition~22 hours (press-derived)
Permanent data loss (G-Drive, no backup)~858 TB (press-derived)
Government officials whose data was lost~125,000 (press-derived)
Systems restored mid-recovery~231 systems (~32.5%) (press-derived)
Negligence charges filed5 charged (press-derived)
Firefighting resources deployed~101 firefighters, ~31 apparatus (press-derived)

Sequence of events

  1. TRIGGER UPS lithium-ion battery bank (reported LG Energy Solution, 384 modules) installed at NIRS Daejeon 5th-floor server/UPS room — the asset that later failed (press-derived, single-source secondary, unverified at review)
  2. TRIGGER Battery bank reportedly passes its last safety inspection despite being past its ~10-year recommended service life (press-derived secondary, unverified at review)
  3. TRIGGER Worker switches OFF the UPS lithium-ion battery power to begin disconnection for relocation from the 5th floor to the basement — ~40 min before ignition, derived from the verified 20:20 timestampChange owner
  4. DETECTION First fire report from the 5th-floor server room (human-noticed; no automated detection-alarm time or battery off-gas early-warning disclosed in any source)
  5. CASCADE Sparks fly from the battery for an 'unknown reason' (미상의 이유); thermal runaway/explosion ignites the fire; one worker suffers 1st-degree burns to face and arm
  6. CASCADE Single-cell failure reportedly cascades runaway through all 384 modules; self-oxidising chemistry drives repeated re-ignition; peak reported >160°C (press-derived secondary)
  7. MITIGATION Fire authorities dispatch immediately — reported ~101 firefighters and ~31 apparatus; an ~20-person task force including lithium-battery experts formed (press-derived secondary)Fire & rescue commander
  8. MITIGATION Crews constrained from water flooding to avoid destroying the protected servers ('데이터를 보관하는 장비의 손상 우려'); rely on gas/CO2, which cannot arrest the self-oxidising runawayFire & rescue commander
  9. MITIGATION NIRS cuts power to all 647 Daejeon systems — protective mass shutdown as the room's HVAC/CRAC (항온항습장치) is lost, risking server overheatingOperations lead
  10. IMPACT Government online services degrade: approximately 96 government online services interrupted (mobile ID/Government24 auth and related public services)
  11. MITIGATION Initial knockdown reached only after over 10 hours ('초진까지 10시간 이상이 소요'), delayed by the water constraints on the lithium-ion fireFire & rescue commander
  12. RECOVERY Fire reportedly fully extinguished ~22 hours after ignition, following repeated re-ignition characteristic of thermal runaway (press-derived secondary)
  13. IMPACT Authorities reportedly confirm ~858 TB of G-Drive data lost with NO backup; the drive held data for ~125,000 government officials (press-derived, not re-verified at review)
  14. IMPACT Scope reported as widening: hundreds of public-institution systems taken offline; G-Drive cited as the destroyed system without recoverable backup (press-derived)
  15. CASCADE A senior officer of the Digital Government Innovation Office overseeing restoration reportedly dies after a fall near the Sejong complex; ministry reviews possible overwork — NOT a fire casualty (press-derived, not re-verified)
  16. RECOVERY Recovery proceeds with a reported ~32.5% (231 systems) restored; ministries report operations badly disrupted where work materials lived only on G-Drive (press-derived)
  17. RESTORED South Korean police reportedly charge five with professional negligence: one NIRS official, one PM-firm employee, three construction workers; unqualified crew and illegal subcontracting cited (press-derived, not re-verified)Authority / investigator
  18. RESTORED Final determination of the exact battery-failure cause reported as expected; formal investigation ongoing (press-derived)

Response by role

11 roles/6 recorded actions/43 playbook actions across 8 failure modes/no recorded action: First responder, Incident commander, Authorised electrical person, Vendor / upstream provider, Service recovery lead, Safety officer, Customer

What each role did

Roles the sequence of events shows acting; every entry quotes its source line. Select a time to jump to it.

Role
Detect
Contain
Recover
Fire & rescue commanderKorean fire authorities; reported ~101 firefighters and ~31 apparatus
no record
  • Dispatch ~101 firefighters and ~31 apparatus and form a ~20-person task force with battery experts
  • Hold back water to protect the servers and rely on gas/CO2, which cannot arrest the runaway
  • Reach initial knockdown after more than 10 hours, delayed by the water constraints
no record
Operations leadNIRS operators who powered down the Daejeon systems
no record
  • Shuts down all 647 systems after the room's HVAC/CRAC is lost, to avoid server overheating
no record
Change ownerThe worker who switched off the UPS battery to start the relocation
  • Starts disconnecting the battery for the move to the basement about 40 minutes before ignition
no record
no record
Authority / investigatorKorean National Police, which charged five with negligence
no record
no record
  • Charge a NIRS official, a PM-firm employee and three construction workers

Role by role

Recorded actions / playbook actions per role. A role with 0 recorded actions does not appear in the sources.

Whoever noticed the fire at about 20:15 — not named — Meets the first alarm: on-shift technician or security in a facility, on-call engineer in a service.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Detect
  • FM-01Call the fire service on the first spark or smoke report from the battery area, before sending anyone to lookNFPA 855
  • FM-04Log the time of first alarm and the call to fire service, so the warning gap can be measuredNFPA 72
Contain
  • FM-02Pull the crew back from the battery on any spark, smell or heat and call the fire serviceNFPA 855

No incident commander is named in the record — Owns every decision until formally relieved: site duty manager on scene, or the declared IC of a service incident.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Detect
  • FM-05Agree at the first hour whether servers or fire control come first; a decision delayed lets runaway re-igniteNIMS / ICS
  • FM-08Track restored share against the plan each day, and flag slippageISO 22301
Contain
  • FM-01Evacuate the floor, get a head count, and tell the fire service the battery is Li-ion and its state of chargeNIMS / ICS
  • FM-07Put the no-backup stores first in line for protection and salvage during a fireISO 22301
  • FM-03Halt any energy-storage job where the crew is not the one tenderedNIMS / ICS
  • FM-04Treat any battery off-gas alarm as a fire: evacuate and isolate before it is confirmedNFPA 72
  • FM-06Tell ministries which services stop and for how long before the power goesISO 22301
Recover
  • FM-08Set shifts and rest for restoration staff; do not run them to exhaustionISO 22301Lesson #6

Korean fire authorities; reported ~101 firefighters and ~31 apparatus — External incident commander for fire, rescue and hazardous materials; works in unified command with the site.

On the record

  1. Dispatch ~101 firefighters and ~31 apparatus and form a ~20-person task force with battery expertsFire authorities dispatch immediately
  2. Hold back water to protect the servers and rely on gas/CO2, which cannot arrest the runawayCrews constrained from water flooding to avoid destroying the protected servers
  3. Reach initial knockdown after more than 10 hours, delayed by the water constraintsInitial knockdown reached only after over 10 hours

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-05Pre-plan with NIRS the water or immersion cooling route for the Li-ion room, so crews know what may be sacrificedNFPA 855Correction of errors #5
Contain
  • FM-01Apply sustained water cooling to the battery bank, accepting server damage, and hold a long watch for re-ignitionNFPA 855
  • FM-05Switch to copious water cooling once gas is seen not to arrest the runawayNFPA 855
Recover
  • FM-04Hand the room back only when off-gas and cell temperature readings are stableNFPA 855

The relocation crew that disconnected the UPS batteries — not named — Switching, isolation and lock-out of power sources, and safe re-energisation.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-01Retire Li-ion banks at end of life and never relocate a past-life packNFPA 855Correction of errors #1
  • FM-02Prove the auxiliary feed to the battery backup is open and test for absence of voltage before touching a cableNFPA 70E
  • FM-04Install battery off-gas and thermal-runaway detection and rated fire separation between Li-ion storage and server hallsNFPA 855Correction of errors #3
  • FM-06Give each hall its own power and cooling and fault-isolate it, so one room's fire does not force a site-wide shutdownUptime OSImprovement #5
Recover
  • FM-02Return no battery to service until its charge, insulation and wiring are re-inspectedNFPA 855

NIRS operators who powered down the Daejeon systems — Technical lead who diagnoses and drives the fix; the subject-matter expert at the keyboard or the switchboard.

On the record

  1. Shuts down all 647 systems after the room's HVAC/CRAC is lost, to avoid server overheatingNIRS cuts power to all 647 Daejeon systems

Playbook analyst guidance by failure mode, not a record of what happened

Detect
  • FM-07Keep a register of systems with no recoverable copy and review it with the facility risk listISO 22301
  • FM-06Watch cooling status per room and decide the shutdown scope from a prepared map of which systems share which coolingASHRAE TC 9.9
Contain
  • FM-05De-energise the room and its equipment so water can be applied safelyNFPA 70E
  • FM-06Shut down only the systems sharing the failed cooling, in priority order, and keep the rest runningISO 22301

The worker who switched off the UPS battery to start the relocation — Authored or approved the change, deployment or configuration push that started the event.

On the record

  1. Starts disconnecting the battery for the move to the basement about 40 minutes before ignitionWorker switches OFF the UPS lithium-ion battery power to begin disconnection for relocation

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-03Require named, qualified individuals on the permit and check them at the gate against employment recordsUptime OS
Detect
  • FM-02Check state of charge and insulation materials at the start; stop the job if cells are at 80-90% or the aux feed is liveNFPA 70E

Tender-winning firms that subcontracted the move to three others — Third party whose product, service or network sits in the failure path.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-03Do the move with the battery manufacturer or a certified crew and no second-tier subcontractorCorrection of errors #4

MOIS and NIRS teams restoring the 647 systems — Restores customer service: failover, workload moves, capacity, backlog drain.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-07Test a restore of a sample of G-Drive from the offsite copy on a scheduleNIST SP 800-34Improvement #3
  • FM-08Write and drill a restoration runbook with priority tiers and cooling-first sequencingISO 22301Improvement #6
Contain
  • FM-08Restore Grade-1 services first and publish progress by tierISO 22301
Recover
  • FM-01Move the surviving racks out of the heat and smoke zone and assess each before any power-upNFPA 855
  • FM-07Salvage what exists on user machines and reconstruct documents with each ministryNIST SP 800-34
  • FM-05Recover servers from the room after water exposure, and prioritise those with no other copyNIST SP 800-34
  • FM-06Restore cooling first, then bring up Grade-1 services in the tiered orderImprovement #6

No safety officer or permit-holder is named for the relocation — Head count, exclusion zones, PPE and the go / no-go for re-entry.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-01Add cell-level impedance, off-gas and thermal diagnostics to the inspection, since a pass/fail check gave false assuranceNFPA 855Lesson #4
  • FM-02Issue a hazardous-work permit that needs verified de-energisation, discharge and thermal monitoring before any Li-ion relocationNFPA 855Improvement #1
  • FM-04Place thermal monitoring on the batteries during any relocation or decommissioningNFPA 855Improvement #1
  • FM-05Put Li-ion energy storage in its own fire-rated room with battery-appropriate suppression, separated from IT spaceNFPA 855Improvement #2
Detect
  • FM-03Audit who is on site against the tender at the start of each shift on critical-infrastructure workUptime OS

Korean National Police, which charged five with negligence — Regulator, investigator or court that establishes cause and obligations after the event.

On the record

  1. Charge a NIRS official, a PM-firm employee and three construction workersSouth Korean police reportedly charge five with professional negligence

Playbook analyst guidance by failure mode, not a record of what happened

Recover
  • FM-03Examine the tender and employment records of the firms, and resolve the chargesCorrection of errors #6

Ministries and agencies using the Daejeon systems and G-Drive — The tenant or service user: their own redundancy, backups and continuity plan.

On the record

No action by this role appears in the sources.

Playbook analyst guidance by failure mode, not a record of what happened

Prevent
  • FM-07Back up G-Drive to a separate site, dropping the exception for being too large to back upNIST SP 800-34Correction of errors #2
  • FM-06Spread critical services over multiple facilities or zones so one fire does not stop the nationISO 22301Improvement #4
Contain
  • FM-08Run each ministry's work on manual fallback for services not yet restoredISO 22301

Failure mode & effects analysis (FMEA)

The NIRS Daejeon government data center during relocation of a lithium-ion UPS battery bank: the battery asset, its isolation and discharge before handling, the contractor chain doing the work, battery-level detection, suppression and firefighting in a server room, the shared power and cooling that set how many systems went down, the G-Drive repository that had no backup, and the restoration effort. The ignition trigger is officially undetermined ('for an unknown reason'); the negligence findings (auxiliary power still connected, cells at 80-90% charge, unqualified crew, illegal subcontracting) come from press reporting of police statements, not a published forensic report; and many technical specifics (battery make, 384 modules, 2014 install, June 2025 inspection, ~22 h full extinguishment, 858 TB) are single-source or press-derived and not re-verified at review. Every corrective action in the dossier is 'Proposed' or 'In progress', none stated as done or committed by NIRS, so no revised score is claimed: all eight modes are residual risk.

8 failure modes/6 high priority/0 of 8 with a published action/total RPN 2906 → 2906 (−0%)

RPN = S × O × D, worst first. Thin bar: after the published action.
FM-01no published action540
FM-07no published action486
FM-02no published action432
FM-03no published action384
FM-04no published action336
FM-05no published action288
FM-08no published action224
FM-06no published action216
Severity × occurrence. Lines bound the medium and high zones.
1122334455667788991010Occurrence →Severity →FM-01 A battery sparks for an undetermined reason during relocation work and thermal runaway propagates through the bank, causing an explosion and fire (S10 O6 D9)01FM-06 The fire knocks out the room's HVAC/CRAC and NIRS powers down all 647 systems to prevent overheating (S9 O4 D6)06FM-02 Batteries are moved while an auxiliary power system to the UPS battery backup remains energised and the cells sit at about 80-90% charge, without the required insulation materials (S9 O6 D8); FM-07 The repository has no backup or external copy, so its destruction in the fire is permanent (S9 O6 D9)02, 07FM-03 The relocation is illegally subcontracted to crews with no battery-relocation experience, and battery manufacturers are excluded to cut costs (S8 O6 D8); FM-05 Gas/CO2 cannot arrest the self-oxidising runaway and water is held back to protect the servers, so the fire re-ignites and burns for hours (S8 O6 D6)03, 05FM-08 Restoration runs for weeks: ~32.5% of systems back mid-recovery and 70.5% of services by 24 October (S7 O4 D8)08FM-04 No battery off-gas or thermal-runaway early warning is disclosed; the event is noticed by people (S7 O6 D8)04
Caught only after impactD ≥ 8
6 of 8
Actions that cut occurrenceO lowered
0
Actions that cut detectionD lowered
0
Actions that cut severityblast radius unchanged
0
FM-01 A battery sparks for an undetermined reason during relocation work and thermal runaway propagates through the bank, causing an explosion and fireLithium-ion UPS battery bank, 5th-floor server/UPS room 10·6·9 540 —
Function
Store UPS energy safely, including while it is disconnected and moved
Effect
Fire in the server room; one worker suffers first-degree burns to face and arm; 96 systems, including the G-Drive store, are destroyed
Cause
Officially undetermined. Reported contributing conditions: an asset ~11 years old against a ~10-year recommended life (single-source, unverified) and handling while energised and highly charged (FM-02)
Prevention in place
A safety inspection reportedly passed in June 2025 (single-source, unverified)
Detection in place
None recorded at battery level; the fire was noticed by people
S 10
Rubric 10, hazard to people: a worker was burned, and the explosion destroyed 96 systems in an occupied government facility.
O 6
Moving an ageing, charged Li-ion bank without the recorded safeguards is a foreseeable condition, weakly guarded: 'occasional'. Held at 6 because the cell-level trigger is unknown and the age figure is single-source.
D 9
A reportedly passed inspection three months earlier did not reveal the hazard, and no battery-level monitoring is recorded; the failure was known only when sparks and fire appeared.

Corrective action

  • Retire UPS Li-ion banks at or before end of recommended life and ban relocation of past-life packs (status: proposed) Correction of errors #1

Who acts — playbook

Prevent
  • Authorised electrical person Retire Li-ion banks at end of life and never relocate a past-life packNFPA 855Correction of errors #1
  • Safety officer Add cell-level impedance, off-gas and thermal diagnostics to the inspection, since a pass/fail check gave false assuranceNFPA 855Lesson #4
Detect
  • First responder Call the fire service on the first spark or smoke report from the battery area, before sending anyone to lookNFPA 855
Contain
  • Incident commander Evacuate the floor, get a head count, and tell the fire service the battery is Li-ion and its state of chargeNIMS / ICS
  • Fire & rescue commander Apply sustained water cooling to the battery bank, accepting server damage, and hold a long watch for re-ignitionNFPA 855
Recover
  • Service recovery lead Move the surviving racks out of the heat and smoke zone and assess each before any power-upNFPA 855

Evidence

  • Sequence of events #52025-09-26 ~20:20 KST — Sparks fly from the battery for an 'unknown reason' (미상의 이유); thermal runaway/explosion ignites the fire; one worker suffers 1st-degree burns to face and arm
  • Reference #8 · press“미상의 이유로 배터리에서 불꽃이 튀며 화재가 발생”
  • Metric #4Fire casualties: 1 worker (1st-degree burns, face/arm)
  • Metric #6Battery age vs recommended life: ~11 years (installed Aug 2014) vs ~10-yr recommended (press-derived)
  • Sequence of events #22025-06 — Battery bank reportedly passes its last safety inspection despite being past its ~10-year recommended service life (press-derived secondary, unverified at review)
  • Root cause“the exact ignition trigger was officially still undetermined and under forensic testing”
FM-07 The repository has no backup or external copy, so its destruction in the fire is permanentG-Drive government cloud repository (backup and DR) 9·6·9 486 —
Function
Keep ministries' working documents recoverable after any single-site loss
Effect
All G-Drive documents for up to 30 ministries are permanently lost (~858 TB, press-derived); ministries report operations badly disrupted where work lived only on G-Drive
Cause
Backup reportedly judged impractical 'due to its large capacity'; a disaster-recovery governance decision
Prevention in place
None
Detection in place
None that flagged the exemption as unacceptable; the loss was confirmed after the fire
S 9
Permanent, unrecoverable loss of a multi-ministry repository: at least the rubric's 9. Not 10 because the rubric reserves 10 for hazard to people or loss of a facility or several regions.
O 6
The no-backup exemption was the normal state of the system; it turns any destructive event at the site into permanent loss. Scored 6 rather than higher because it still needs that event.
D 9
The gap was a known design choice, but no control treated it as a risk to act on; the loss was surfaced only through impact.

Corrective action

  • Real backup and geographically separate DR for all critical government stores, removing the 'too large to back up' exemption (status: proposed) Correction of errors #2
  • Isolated, tested, recoverable backups and cross-site replication for shared government repositories (analyst recommendation) Improvement #3

Who acts — playbook

Prevent
  • Customer Back up G-Drive to a separate site, dropping the exception for being too large to back upNIST SP 800-34Correction of errors #2
  • Service recovery lead Test a restore of a sample of G-Drive from the offsite copy on a scheduleNIST SP 800-34Improvement #3
Detect
  • Operations lead Keep a register of systems with no recoverable copy and review it with the facility risk listISO 22301
Contain
  • Incident commander Put the no-backup stores first in line for protection and salvage during a fireISO 22301
Recover
  • Service recovery lead Salvage what exists on user machines and reconstruct documents with each ministryNIST SP 800-34

Evidence

  • Contributing factor #5No battery backup for the ~858 TB G-Drive ('couldn't have a backup system due to its large capacity') — a disaster-recovery governance failure that converted a contained fire into permanent data loss for ~125,000 officials (Anadolu/DCD, press-derived).
  • Reference #7 · press“The G-Drive couldn't have a backup system due to its large capacity”
  • Reference #13 · news“all documents stored on the repository have been lost”
  • Metric #8Permanent data loss (G-Drive, no backup): ~858 TB (press-derived)
  • Sequence of events #16~2025-10 (week of) — Recovery proceeds with a reported ~32.5% (231 systems) restored; ministries report operations badly disrupted where work materials lived only on G-Drive (press-derived)
FM-02 Batteries are moved while an auxiliary power system to the UPS battery backup remains energised and the cells sit at about 80-90% charge, without the required insulation materialsElectrical isolation and discharge before battery relocation 9·6·8 432 —
Function
Make the batteries electrically isolated and energetically safe before anyone handles them
Effect
Workers handle a pack holding near-maximum stored energy that is still connected; the ignition follows about 40 minutes after the battery power is switched off
Cause
Safety protocols not followed: no full discharge, no required insulation, auxiliary connection left live (police findings via press)
Prevention in place
Building main power was disconnected; the auxiliary path was not
Detection in place
None recorded before the fire
S 9
This is the route by which the work put stored energy next to people; scored one step below FM-01 so the single fire is not counted twice at full weight.
O 6
A missed isolation step and an undischarged pack during non-routine work is a foreseeable slip, weakly guarded: 'occasional'.
D 8
No verification of de-energisation or state of charge is recorded; the omissions were established by police after the fire.

Corrective action

  • Require certified crews and verified full de-energisation before any disconnection (status: proposed) Correction of errors #1
  • Hazardous-work permits, verified de-energisation and physical isolation for Li-ion relocation (analyst recommendation) Improvement #1

Who acts — playbook

Prevent
  • Safety officer Issue a hazardous-work permit that needs verified de-energisation, discharge and thermal monitoring before any Li-ion relocationNFPA 855Improvement #1
  • Authorised electrical person Prove the auxiliary feed to the battery backup is open and test for absence of voltage before touching a cableNFPA 70E
Detect
  • Change owner Check state of charge and insulation materials at the start; stop the job if cells are at 80-90% or the aux feed is liveNFPA 70E
Contain
  • First responder Pull the crew back from the battery on any spark, smell or heat and call the fire serviceNFPA 855
Recover
  • Authorised electrical person Return no battery to service until its charge, insulation and wiring are re-inspectedNFPA 855

On the record at this failure

  • Change owner Starts disconnecting the battery for the move to the basement about 40 minutes before ignition

Evidence

  • Reference #5 · press“an auxiliary power system connected to the data center's Uninterruptible Power Supply (UPS) battery backup system was not”
  • Reference #6 · press“failed to fully discharge the batteries before moving them”
  • Root cause“sat at roughly 80-90% state of charge”
  • Sequence of events #32025-09-26 ~19:40 KST — Worker switches OFF the UPS lithium-ion battery power to begin disconnection for relocation from the 5th floor to the basement — ~40 min before ignition, derived from the verified 20:20 timestamp
  • Contributing factor #3Safety protocol not followed during disconnection — plausibly disconnecting wiring before the pack was fully de-energised, producing an arc/voltage spike; ko.wikipedia (verified) labels the spark cause 'unknown,' and the arc hypothesis is secondary (breached.company).
FM-03 The relocation is illegally subcontracted to crews with no battery-relocation experience, and battery manufacturers are excluded to cut costsContractor qualification and subcontracting chain 8·6·8 384 —
Function
Ensure energy-storage work is done by qualified, accountable crews
Effect
Unqualified workers perform the high-energy task; five people are reportedly charged with professional negligence and NIRS is raided
Cause
Two tender-winning firms passed the work to three other businesses in breach of Korean law and falsified employment records (press reporting of police findings)
Prevention in place
Public tender process, which the subcontracting bypassed
Detection in place
Found after the fire by the police investigation
S 8
A governance precursor whose consequence runs through FM-02 and FM-01; scored at 8 so the fire is not counted at full weight a third time.
O 6
Cost-driven subcontracting with falsified records defeated the qualification check, a weakly guarded condition: 'occasional'.
D 8
Falsified employment records hid the subcontracting; it surfaced only in the post-fire police investigation.

Corrective action

  • Prohibit illegal subcontracting and enforce contractor qualification checks and safety sign-off for energy-storage handling (status: proposed) Correction of errors #4

Who acts — playbook

Prevent
  • Vendor / upstream provider Do the move with the battery manufacturer or a certified crew and no second-tier subcontractorCorrection of errors #4
  • Change owner Require named, qualified individuals on the permit and check them at the gate against employment recordsUptime OS
Detect
  • Safety officer Audit who is on site against the tender at the start of each shift on critical-infrastructure workUptime OS
Contain
  • Incident commander Halt any energy-storage job where the crew is not the one tenderedNIMS / ICS
Recover
  • Authority / investigator Examine the tender and employment records of the firms, and resolve the chargesCorrection of errors #6

On the record at this failure

  • Authority / investigator Charge a NIRS official, a PM-firm employee and three construction workers

Evidence

  • Contributing factor #1Unqualified, inexperienced personnel performing the Li-ion relocation: police reportedly found the crew had no experience with large-scale battery relocations and deemed them unqualified (Anadolu, press-derived, not re-verified at review).
  • Contributing factor #2Illegal subcontracting of the relocation work reportedly broke the qualification/accountability chain (Anadolu, press-derived).
  • Root cause“the battery manufacturers were deliberately excluded to cut costs”
  • Sequence of events #172025-10-22 — South Korean police reportedly charge five with professional negligence: one NIRS official, one PM-firm employee, three construction workers; unqualified crew and illegal subcontracting cited (press-derived, not re-verified)
  • Metric #11Negligence charges filed: 5 charged (press-derived)
FM-04 No battery off-gas or thermal-runaway early warning is disclosed; the event is noticed by peopleBattery-level and room fire detection 7·6·8 336 —
Function
Catch cell venting or thermal runaway before open flame
Effect
No pre-flame warning; the first report is human-noticed at ~20:15 KST
Cause
Detection type (aspirating, spot or off-gas) and any automated alarm time are not disclosed in any source
Prevention in place
None recorded
Detection in place
Human report
S 7
Removes the warning window rather than causing the fire, so it is scored below FM-01; losing it on a Li-ion bank next to production servers is a major degradation of protection.
O 6
No early-warning layer is recorded for a battery being worked on, a standing condition weakly guarded: 'occasional'. Not higher because absence is undisclosed rather than proven.
D 8
The only recorded detection is people noticing the fire: 'detected after impact'.

Corrective action

  • Battery-level off-gas and thermal-runaway early-warning detection (status: proposed) Correction of errors #3
  • Dedicated fire-rated battery rooms with early-warning gas/thermal detection (analyst recommendation) Improvement #2

Who acts — playbook

Prevent
  • Authorised electrical person Install battery off-gas and thermal-runaway detection and rated fire separation between Li-ion storage and server hallsNFPA 855Correction of errors #3
  • Safety officer Place thermal monitoring on the batteries during any relocation or decommissioningNFPA 855Improvement #1
Detect
  • First responder Log the time of first alarm and the call to fire service, so the warning gap can be measuredNFPA 72
Contain
  • Incident commander Treat any battery off-gas alarm as a fire: evacuate and isolate before it is confirmedNFPA 72
Recover
  • Fire & rescue commander Hand the room back only when off-gas and cell temperature readings are stableNFPA 855

Evidence

  • Sequence of events #42025-09-26 ~20:15 KST — First fire report from the 5th-floor server room (human-noticed; no automated detection-alarm time or battery off-gas early-warning disclosed in any source)
  • Contributing factor #9No disclosed battery-level off-gas/thermal-runaway early-warning detection; the event was human-noticed at ~20:15 rather than caught at cell venting (ko.wikipedia, verified).
  • Technical deep-dive“Detection specifics (VESDA/aspirating, spot smoke/heat, or battery off-gas detection) and any automated-alarm time are NOT disclosed in any source”
FM-05 Gas/CO2 cannot arrest the self-oxidising runaway and water is held back to protect the servers, so the fire re-ignites and burns for hoursSuppression and firefighting in the server room 8·6·6 288 —
Function
Extinguish a battery fire quickly without destroying the equipment the room protects
Effect
Initial knockdown takes more than 10 hours; full extinguishment reportedly ~22 hours after ignition; ~101 firefighters and ~31 apparatus deployed
Cause
Server-hall suppression doctrine mismatched to Li-ion chemistry; the only reliable tactic, copious water or immersion, conflicts with protecting data equipment
Prevention in place
Fixed server-room suppression (type not disclosed), which did not arrest the event
Detection in place
Visible to responders at onset
S 8
Sets the duration and extent of the fire rather than its start; the worker injury is carried by FM-01, so this is scored at 8.
O 6
Gas-and-cautious-water doctrine is the standing regime for this room, and it fails whenever a Li-ion runaway occurs there: 'occasional'.
D 6
Responders saw at once that the fire was not being arrested, but had no tactic that stopped it: 'detected at onset, not prevented'.

Corrective action

  • Li-ion-appropriate fire-response doctrine with immersion/copious-water cooling capability (status: proposed) Correction of errors #5

Who acts — playbook

Prevent
  • Fire & rescue commander Pre-plan with NIRS the water or immersion cooling route for the Li-ion room, so crews know what may be sacrificedNFPA 855Correction of errors #5
  • Safety officer Put Li-ion energy storage in its own fire-rated room with battery-appropriate suppression, separated from IT spaceNFPA 855Improvement #2
Detect
  • Incident commander Agree at the first hour whether servers or fire control come first; a decision delayed lets runaway re-igniteNIMS / ICS
Contain
  • Fire & rescue commander Switch to copious water cooling once gas is seen not to arrest the runawayNFPA 855
  • Operations lead De-energise the room and its equipment so water can be applied safelyNFPA 70E
Recover
  • Service recovery lead Recover servers from the room after water exposure, and prioritise those with no other copyNIST SP 800-34

On the record at this failure

  • Fire & rescue commander Hold back water to protect the servers and rely on gas/CO2, which cannot arrest the runaway
  • Fire & rescue commander Reach initial knockdown after more than 10 hours, delayed by the water constraints

Evidence

  • Sequence of events #82025-09-26 evening — Crews constrained from water flooding to avoid destroying the protected servers ('데이터를 보관하는 장비의 손상 우려'); rely on gas/CO2, which cannot arrest the self-oxidising runaway
  • Sequence of events #112025-09-27 early AM — Initial knockdown reached only after over 10 hours ('초진까지 10시간 이상이 소요'), delayed by the water constraints on the lithium-ion fire
  • Metric #3Time to initial knockdown (초진): >10 hours
  • Metric #7Time to full extinguishment after ignition: ~22 hours (press-derived)
  • Contributing factor #7Suppression regime mismatched to chemistry: server-hall water-cautious firefighting could not arrest a self-oxidising Li-ion runaway, driving the verified >10h initial knockdown (ko.wikipedia).
  • Metric #12Firefighting resources deployed: ~101 firefighters, ~31 apparatus (press-derived)
FM-08 Restoration runs for weeks: ~32.5% of systems back mid-recovery and 70.5% of services by 24 OctoberService restoration 7·4·8 224 —
Function
Restore national services in priority order within days
Effect
Government services stay partly unavailable for weeks; a senior official overseeing restoration reportedly dies amid overwork concerns (press-derived; not a fire casualty)
Cause
Restoration of 647 systems at one site with 96 destroyed, without a recorded pre-drilled restoration runbook
Prevention in place
Priority tiers existed in practice (34 of 40 Grade-1 services restored by the 70.5% mark)
Detection in place
Known during recovery
S 7
Sets the duration of the outage that FM-06 carries rather than causing it; weeks of partial service is a major degradation.
O 4
Exercised only after a site-wide event of this scale: 'infrequent'.
D 8
No restoration drill is recorded, so the recovery time was learned after impact.

Corrective action

  • Pre-defined, drilled restoration runbook with priority tiers and cooling-first sequencing (analyst recommendation) Improvement #6

Who acts — playbook

Prevent
  • Service recovery lead Write and drill a restoration runbook with priority tiers and cooling-first sequencingISO 22301Improvement #6
Detect
  • Incident commander Track restored share against the plan each day, and flag slippageISO 22301
Contain
  • Service recovery lead Restore Grade-1 services first and publish progress by tierISO 22301
  • Customer Run each ministry's work on manual fallback for services not yet restoredISO 22301
Recover
  • Incident commander Set shifts and rest for restoration staff; do not run them to exhaustionISO 22301Lesson #6

Evidence

  • Metric #10Systems restored mid-recovery: ~231 systems (~32.5%) (press-derived)
  • Reference #15 · news“34 out of 40 'Grade 1' services... have been restored”
  • Sequence of events #152025-10-03/04 — A senior officer of the Digital Government Innovation Office overseeing restoration reportedly dies after a fall near the Sejong complex; ministry reviews possible overwork — NOT a fire casualty (press-derived, not re-verified)
  • Sequence of events #16~2025-10 (week of) — Recovery proceeds with a reported ~32.5% (231 systems) restored; ministries report operations badly disrupted where work materials lived only on G-Drive (press-derived)
FM-06 The fire knocks out the room's HVAC/CRAC and NIRS powers down all 647 systems to prevent overheatingShared power and cooling failure domain at Daejeon HQ 9·4·6 216 —
Function
Confine the effect of a one-room fire to that room's systems
Effect
Digital ID, postal banking, emergency GPS tracking, courts and tax systems paralysed nationwide; 709 services disrupted
Cause
Power and cooling shared across the co-located estate, with no fault isolation per hall
Prevention in place
None recorded
Detection in place
Known at onset; the mass power-down was a deliberate protective action
S 9
Nationwide outage of foundational government services with no workaround: the rubric's 9. Not 10 because this step itself hazarded no one.
O 4
The shared domain is a standing design condition but only cascades when a fire takes out the room's cooling: 'infrequent'.
D 6
NIRS saw the cooling loss and chose the shutdown at onset; nothing contained it: 'detected at onset, not prevented'.

Corrective action

  • Pre-plan power and cooling failure domains to bound outage blast radius (status: proposed) Correction of errors #5
  • Fire zoning with independent power and cooling per hall (analyst recommendation) Improvement #5
  • Geo-replicate critical national services across facilities (analyst recommendation) Improvement #4

Who acts — playbook

Prevent
  • Authorised electrical person Give each hall its own power and cooling and fault-isolate it, so one room's fire does not force a site-wide shutdownUptime OSImprovement #5
  • Customer Spread critical services over multiple facilities or zones so one fire does not stop the nationISO 22301Improvement #4
Detect
  • Operations lead Watch cooling status per room and decide the shutdown scope from a prepared map of which systems share which coolingASHRAE TC 9.9
Contain
  • Operations lead Shut down only the systems sharing the failed cooling, in priority order, and keep the rest runningISO 22301
  • Incident commander Tell ministries which services stop and for how long before the power goesISO 22301
Recover
  • Service recovery lead Restore cooling first, then bring up Grade-1 services in the tiered orderImprovement #6

On the record at this failure

  • Operations lead Shuts down all 647 systems after the room's HVAC/CRAC is lost, to avoid server overheating

Evidence

  • Sequence of events #92025-09-26 night — NIRS cuts power to all 647 Daejeon systems — protective mass shutdown as the room's HVAC/CRAC (항온항습장치) is lost, risking server overheating
  • Contributing factor #8Loss of HVAC/CRAC (항온항습장치) forced a protective mass power-down of 647 systems, widening the outage well beyond the fire's footprint (ko.wikipedia, verified).
  • Metric #1Systems powered off at Daejeon HQ: 647 systems
  • Reference #15 · news“500 out of 709 services disrupted by the fire”
  • Technical deep-dive“the outage was driven as much by the deliberate mass power-down and lost cooling as by flame”
Scoring rubric and method

Scales adapted from IEC 60812:2018 and AIAG-VDA. RPN = S × O × D. High: S ≥ 9 with O ≥ 4 or D ≥ 7, or RPN ≥ 300. Medium: RPN ≥ 120 or S ≥ 7. Severity overrides the product: 9 × 2 × 9 = 162 would otherwise hide a region-wide outage nothing could catch. Quotes are checked verbatim against this dossier; a revised score needs a published action. RZ analyst assessment, not an operator document.

Severity

10Hazard to people, or loss of the facility / several regions
9Region-wide or provider-wide outage of a foundational service, no workaround
8Full outage of a major service for hours
7Major degradation of a major service
6Partial outage confined to one zone or one service
5Customer-visible degradation
4Limited customer impact
3Internal impact only
2Negligible
1No effect

Occurrence

10Near certain: the cause is present in normal operation
8Frequent: routine work exercises the cause
6Occasional: a foreseeable slip or condition, weakly guarded
4Infrequent: needs an unusual combination
2Remote: guarded by design
1Eliminated by design

Detection

10No control could detect it
9Detected only through customer impact
8Detected after impact by internal monitoring
6Detected at onset, not prevented
4Detected before impact with time to act
2Automated interlock almost certainly stops it
1Certain to be stopped

Root cause and contributing factors

At approximately 20:20 KST on 2025-09-26 a fire broke out in the fifth-floor UPS room of the National Information Resources Service (NIRS) headquarters in Yuseong-gu, Daejeon, during work to physically relocate lithium-ion UPS batteries.
Full root-cause narrative
Per the Korean-language record, a worker switched off the UPS lithium-ion battery power and, about 40 minutes later, sparks flew from a battery 'for an unknown reason' (미상의 이유로) and ignited the fire — so the exact ignition trigger was officially still undetermined and under forensic testing, even though the surrounding negligence was established. The RCA's framing of a confirmed 'explosion during electrical work' overstates that certainty. Korean National Police investigators concluded the relocation was performed on batteries that were neither electrically isolated nor made energetically safe to handle, and filed professional-negligence charges. Two conditions compounded. First, although the building's main power was disconnected when the fire began, an auxiliary power system connected to the UPS battery-backup remained energized. Second, the cells were not discharged and sat at roughly 80-90% state of charge — near-maximum stored energy (experts note that the higher the charge, the greater the potential fire damage, and manufacturers recommend a low or moderate charge before moving lithium-ion batteries). Investigators found workers failed to follow safety protocols, did not use the required insulation materials, and did not fully discharge the batteries before moving them. Human and procedural safeguards were absent: the staff were not qualified for the job and had no battery-relocation experience; the battery manufacturers were deliberately excluded to cut costs; and the work had been illegally subcontracted — the two firms that won the tender handed it to three other businesses in breach of Korean law, with the two primary contractors falsifying employment records to make the crews appear to be their own staff. Consequences were severe because recovery redundancy was inadequate at the data layer. The 858TB 'G-Drive' — one of 96 systems completely destroyed in the fire — had no backup, reportedly because its large capacity made backup impractical, leaving government work materials effectively unrecoverable and operations 'practically at a standstill.' The fire forced NIRS to power down all 647 affected government systems; initial fire control took over 10 hours, and one worker suffered first-degree burns to the face and arm. Five people were charged with professional negligence resulting in fire — one NIRS official, one project-management-firm worker, and three construction-company employees — with charges reported in late October 2025. Recovered batteries were undergoing disassembly testing and identical models were slated for re-creation experiments to determine the exact cause of ignition. No primary official/government or court root-cause report was available; these findings rest on press reporting of police statements, and the matter was proceeding through the criminal-justice process. Official confirmation. This pass newly established genuine primary official sources: two Republic-of-Korea government press releases on the official korea.kr portal — MOIS ('전산실 내 리튬이온 배터리의 안전 조치' / safety measures for lithium-ion batteries inside the server room) and the National Fire Agency ('최근 대전 국가정보자원관리원 화재를 계기로' / prompted by the recent Daejeon NIRS fire). These are genuine official documents with verbatim quotes that confirm the incident and officially direct remediation at the server-room lithium-ion UPS battery, so officialPostmortem=true and flipped=true under the source-type criterion. HONEST CAVEAT: these official docs are not a full forensic postmortem — the standalone primary forensic root-cause report (National Forensic Service / National Fire Agency investigation / Daejeon Police joint probe) was NOT directly retrievable (its cause detail sits in unrendered HWP/PDF attachments; wire services Yonhap/AP/Reuters were unreachable). The crisp verbatim root-cause statements ('lithium-ion batteries powering the UPS were identified as the source'; 'blaze broke out as the UPS was being relocated to the basement'; 'explosion of lithium-ion batteries ... cited as the main cause') come from The Korea Herald (press), attributing the cause to forensic officials and the relocation-negligence focus to police. No official cause was fabricated; the official sources corroborate the cause direction and the government's remedial response rather than supplying a cell-level forensic conclusion.

Contributing factors by category

Contributing factors by category — NIRS DaejeonEquipment: Li-ion bank past 10 years. Design: Li-ion bank beside servers; Shared power and cooling; No G-Drive backup; No cell-level detection. Process: Isolation steps skipped; Water-cautious fire doctrine. People: Crew had no battery experience. External: Illegal subcontracting. Effect: 647 systems offline, G-Drive lost.647 systems offline, G-Drive lostDesignLi-ion bank beside serversShared power and coolingNo G-Drive backupNo cell-level detectionEquipmentLi-ion bank past 10 yearsExternalIllegal subcontractingProcessIsolation steps skippedWater-cautious fire doctrinePeopleCrew had no battery experience
Each short label stands for a contributing factor or failure mode recorded in this dossier; the full sentences are listed below.
  • Unqualified, inexperienced personnel performing the Li-ion relocation: police reportedly found the crew had no experience with large-scale battery relocations and deemed them unqualified (Anadolu, press-derived, not re-verified at review).
  • Illegal subcontracting of the relocation work reportedly broke the qualification/accountability chain (Anadolu, press-derived).
  • Safety protocol not followed during disconnection — plausibly disconnecting wiring before the pack was fully de-energised, producing an arc/voltage spike; ko.wikipedia (verified) labels the spark cause 'unknown,' and the arc hypothesis is secondary (breached.company).
  • Aged asset kept in service and physically relocated rather than retired: reported as an LG Energy Solution bank installed August 2014, ~11 years old and past ~10-year recommended life (breached.company, single-source secondary, unverified at review).
  • No battery backup for the ~858 TB G-Drive ('couldn't have a backup system due to its large capacity') — a disaster-recovery governance failure that converted a contained fire into permanent data loss for ~125,000 officials (Anadolu/DCD, press-derived).
  • Physical siting of a volatile Li-ion bank close to production servers with inadequate fire separation, exposing adjacent racks to runaway heat and smoke (breached.company, secondary).
  • Suppression regime mismatched to chemistry: server-hall water-cautious firefighting could not arrest a self-oxidising Li-ion runaway, driving the verified >10h initial knockdown (ko.wikipedia).
  • Loss of HVAC/CRAC (항온항습장치) forced a protective mass power-down of 647 systems, widening the outage well beyond the fire's footprint (ko.wikipedia, verified).
  • No disclosed battery-level off-gas/thermal-runaway early-warning detection; the event was human-noticed at ~20:15 rather than caught at cell venting (ko.wikipedia, verified).

Analysis

What happened (verified core)

On the evening of 2025-09-26, during relocation work on a UPS lithium-ion battery in the 5th-floor server/UPS room of the NIRS Daejeon government data center, a worker switched the battery power off and about 40 minutes later, at ~20:20 KST, sparks flew from the battery 'for an unknown reason' and a fire broke out (ko.wikipedia, verified verbatim). A first report came at ~20:15. NIRS powered off all 647 Daejeon systems as the room's HVAC/CRAC failed, and roughly 96 government online services were interrupted. Water suppression was constrained by fear of destroying the data-storage equipment, so initial knockdown took over 10 hours. One worker suffered 1st-degree burns.

Why it became a disaster (governance amplifiers)

The physical fire was contained to a room, but the impact was national. Press reporting (Anadolu/DCD, not re-verifiable at review) states the ~858 TB G-Drive store — data for ~125,000 officials — had no backup 'due to its large capacity,' making its loss permanent, while other destroyed systems were recoverable. Police reportedly charged five people (an NIRS official, a PM-firm employee, three construction workers) with professional negligence, citing an unqualified, inexperienced crew and illegal subcontracting. The disaster scale was manufactured by DR governance, contractor governance, and asset-lifecycle failures, not by the battery alone.

The Li-ion suppression conflict

Lithium-ion thermal runaway is self-oxidising, so clean-agent and water-cautious server-hall firefighting cannot arrest it, and it propagates cell-to-cell. The only reliable tactic — immersion/copious-water cooling — is precisely what a server room forbids to protect equipment. This is the unresolved doctrinal conflict the incident exposes: the verified >10h knockdown (ko.wikipedia) and reportedly ~22h full-out with repeated re-ignition (breached.company, secondary) are the direct symptom. No battery-level off-gas or thermal-runaway early warning was disclosed; the fire was human-noticed, not caught at cell venting.

Sourcing and confidence

High-confidence, verified facts (ko.wikipedia, re-fetched at review): ignition ~20:20 with unknown spark cause, first report ~20:15, worker powered off battery ~40 min prior, 647 systems shut, HVAC/CRAC loss, water-suppression difficulty, >10h knockdown, ~96 services interrupted, 1 worker 1st-degree burns, presumed UPS lithium-battery cause. Press-derived and NOT re-verifiable at review (fetch 403/404, search budget exhausted): 858 TB, no-backup rationale, ~125,000 officials, 5 negligence charges, restoration %, and all breached.company technical specifics (LG Energy Solution, 384 modules, Aug-2014 install, ~60 cm siting, >160°C, ~22h, ~101 firefighters, June-2025 inspection). These are retained as attributed, hedged secondary claims, not established fact.

Technical deep-dive
The event is a textbook demonstration of why lithium-ion energy storage in a server hall defeats the fire-protection assumptions data centers are built on. A conventional server-hall fire regime — clean-agent (inert gas or chemical clean agent) plus cautious or prohibited water application to protect equipment — is designed for combustion that needs external oxygen. A Li-ion cell in thermal runaway is self-oxidising: the decomposing cathode liberates oxygen internally, so smothering agents cannot starve it, and the reaction propagates cell-to-cell as each venting cell heats its neighbours. With the pack reported at 384 modules, once one cell failed during disconnection the runaway chained across the bank (breached.company, secondary). This is why the fire "reignited repeatedly" and why full extinguishment reportedly took ~22 hours after ignition, with initial knockdown alone taking over 10 hours — the >10h figure is verified in ko.wikipedia ("초진까지 10시간 이상이 소요되었다"), while the ~22h full-out and >160°C peak are press-derived secondary. The suppression dilemma is the central operational lesson. The room's fixed suppression did not arrest the event. ko.wikipedia (verified) states water-based firefighting was difficult because of concern over damaging the data-storage equipment, driving the >10-hour initial knockdown. But gas/clean agent cannot quench a self-oxidising runaway, and cautious water cannot rapidly cool cascading modules. The only reliable Li-ion tactic — total immersion / copious water cooling — was the one tactic the room's mission forbade. That unresolved conflict is what this incident exposes. The second dynamic is the de-energisation cascade. NIRS cut power to all 647 Daejeon systems ("647개 시스템"), partly a protective shutdown because the fire and response knocked out the room's HVAC/CRAC (항온항습장치); without cooling and dehumidification, running servers would overheat (ko.wikipedia, verified). So the outage was driven as much by the deliberate mass power-down and lost cooling as by flame — in a dense DC the blast radius of a single-rack event is defined by shared power and cooling topology, not the fire's physical footprint. Detection specifics (VESDA/aspirating, spot smoke/heat, or battery off-gas detection) and any automated-alarm time are NOT disclosed in any source; what is documented is a human-noticed first report at ~20:15 KST and ignition at ~20:20 (ko.wikipedia). No source indicates any battery-level gas or thermal-runaway early-warning system caught cell venting before flame — a detection gap that, for Li-ion, is the difference between a vented cell and a multi-hour fire.

Corrective actions and lessons

Correction of errors

ActionOwnerStatus
Retire and safely dispose of all UPS lithium-ion battery banks at/before end of recommended service life; ban physical relocation of past-life packs; require certified crews and verified full de-energisation before any disconnection.NIRS facilities / MOIS Digital GovernmentProposed
Provision real backup and geographically separate disaster recovery for all critical government stores including G-Drive, removing the 'too large to back up' exemption.MOIS / NIRS DR governanceProposed
Install battery-level off-gas and thermal-runaway early-warning detection and rated fire separation between Li-ion energy storage and production server halls.NIRS facilities engineeringProposed
Prohibit illegal subcontracting on critical-infrastructure work; enforce contractor qualification verification and safety-protocol sign-off for energy-storage handling.MOIS procurement / safetyProposed
Adopt Li-ion-appropriate fire response doctrine (immersion/copious-water cooling capability) and pre-plan power/cooling failure domains to bound outage blast radius.NIRS operations / local fire authorityProposed
Complete formal cause investigation and publish findings; resolve the 5 negligence charges through the courts.Korean National Police / prosecutorsIn progress (press-reported)

Lessons learnt

  • A single-rack lithium-ion event defines its blast radius through shared power and cooling, not flame footprint: the 647-system outage came from the deliberate mass power-down and lost HVAC/CRAC as much as from the fire itself (ko.wikipedia, verified).
  • Server-hall fire doctrine is incompatible with Li-ion chemistry: water-cautious tactics could not arrest a self-oxidising runaway, producing the verified >10h initial knockdown (ko.wikipedia) and reportedly ~22h to full out with repeated re-ignition (breached.company). The one effective tactic — copious water/immersion cooling — is the one the room's mission forbids.
  • 'Too big to back up' is a decision, not a fact: ~858 TB was reportedly lost solely because G-Drive had no backup 'due to its large capacity' (Anadolu/DCD). Storage cost is always cheaper than total sovereign data loss.
  • A passed safety inspection is not proof of battery health: a reportedly passed June 2025 inspection preceded catastrophic runaway (breached.company); pass/fail inspection without cell-level off-gas/impedance/thermal diagnostics gives false assurance.
  • Human factors dominate: the fire is attributed to a disconnection during relocation with the ignition officially 'unknown' (ko.wikipedia) and police reportedly citing unqualified crew and illegal subcontracting (Anadolu) — governance of who touches energy storage matters as much as the hardware.
  • Cascade risk extends beyond the fire: recovery pressure was severe enough that an official overseeing restoration reportedly died amid overwork concerns (techspot) — recovery staffing and welfare must be planned, not improvised.

Improvements

  • Mandate hazardous-work permits, verified de-energization, thermal monitoring and physical isolation for all lithium-ion battery relocation and decommissioning, removing live server rooms from the work zone.
  • Relocate lithium-ion UPS energy storage into dedicated fire-rated battery rooms with early-warning gas/thermal detection and battery-appropriate suppression, separated from IT space.
  • Provision isolated, tested, recoverable backups and cross-site replication for shared government cloud repositories so no single fire can cause permanent multi-ministry data loss.
  • Distribute and geo-replicate critical national services across multiple facilities/availability zones to eliminate single-facility, single-event nationwide paralysis.
  • Compartmentalize and fault-isolate the facility (fire zoning, independent power and cooling per hall) so that a fire in one room does not require a precautionary shutdown of the entire co-located estate.
  • Institutionalize a pre-defined, drilled restoration runbook with priority tiers (Grade-1 services, cooling-first sequencing) and transparent progress reporting.

References and provenance

Quotes are short, attributed, and for provenance only; the analysis is original. Last verified 2026-07-31.